| United States. Court of Claims, Audrey Bernhardt - 1962 - 784 pages
...the Contractor of the notification of change : Provided, however, That the Contracting Officer, if he decides that the facts justify such action, may receive...any time prior to final payment under this contract. Failure to agree to any adjustment shall be a dispute concerning a question of fact within the meaning... | |
| United States. Court of Claims, Audrey Bernhardt - 1959 - 1028 pages
...Contractor of the notification of extra or change : Provided, however, That the Contracting Officer, if he decides that the facts justify such action, may receive,...upon any such claim asserted at any time prior to the date of final settlement of the contract. If the parties fail to agree upon the adjustment to be... | |
| United States. Court of Claims, Audrey Bernhardt - 1968 - 922 pages
...the Contractor of the notification of change : Provided, however, That the Contracting Officer, if he decides that the facts justify such action, may receive and act upon any such claim asserted at any time/prior to final payment under this contract. Failure to agree to any adjustment shall be a dispute... | |
| 1999 - 572 pages
...in such other provisions of the contract as may be so affected, and the contract shall be modified in writing accordingly. Any claim by the Contractor...adjustment, the Contracting Officer shall have the fight to prescribe the manner of disposition of such property. Failure to agree to any adjustment shall... | |
| 1979 - 520 pages
...the Contractor of the notification of change. Provided, however. That the Contracting Officer, if he decides that the facts justify such action, may receive...Where the cost of property made obsolete or excess as result of a change is included in the Contractor's claim for adjustment, the Contracting Officer shall... | |
| 1973 - 944 pages
...the Contractor of the notification of change, provided, however, that the Contracting Officer, If he decides that the facts justify such action, may receive...Where the cost of property made obsolete or excess as result of a change Is Included In the Contractor's claim for adjustment, the Contracting Officer shall... | |
| 1981 - 524 pages
...the Contractor of the notification of change: Provided, however. That the Contracting Officer, if he decides that the facts justify such action, may receive...payment under this contract. Where the cost of property mad* obsolete or excess as a result of a change is included in the Contractor's claim for adjustment,... | |
| 1983 - 1974 pages
...notification of change, prmided, however, that the Contracting Officer, if he decides that the fads justify such action, may receive and act upon any...contract. Where the cost of property made obsolete or esceĀ» aa remit of a change is included in the Contractor's claim for adjustment, the Contracting Officer... | |
| 1988 - 722 pages
...he/she decides that the facts justify such action, may receive and act upon any such claim assert ed at any time prior to final payment under this contract....result of a change is included in the Contractor's clam for adjustment, the Contracting Officer shall have the right to prescribe the manner of disposition... | |
| 1980 - 976 pages
...the Contractor of the notification of change; provided, however, that the Contracting Officer, If he decides that the facts justify such action, may receive...any time prior to final payment under this contract. Failure to agree to any adjustment shall be a dispute concerning a question of fact within the meaning... | |
| |