" Contractor for adjustment under this clause must be asserted within thirty (80) days from the date of receipt by the Contractor of the notification of change: Provided, however. That the Contracting Officer, if he decides that the facts justify such action,... "
The Code of Federal Regulations of the United States of America - Page 202
1989
Full view - About this book

Departments of State and Justice, the Judiciary, and Related Agencies ...

United States. Congress. House. Committee on Appropriations - 1960 - 1290 pages
...the contractor of the notification of change; provided, however, that the contracting officer, if he decides that the facts justify such action, may receive...any time prior to final payment under this contract. Failure to agree to any adjustment shall be a dispute concerning a question of fact within the meaning...
Full view - About this book

Study of Air Force Contract AF 33 (038)-18503, General MOtors Corp., Buick ...

United States. Congress. House. Committee on Armed Services, United States. Congress. House. Committee on Armed Services. Subcommittee for Special Investigations - 1957 - 434 pages
...the Contractor of the notification of change : Prodded, however, That the Contracting Officer, if he decides that the facts justify such action, may receive...any time prior to final Payment under this contract. Failure to agree to any adjustment shall be a dispnte concerning a question of fact within the meaning...
Full view - About this book

Study of Air Force Contract AF33(038)-18503, General Motors Corp.--Buick ...

United States. Congress. House. Committee on Armed Services - 1957 - 436 pages
...the Contractor of the notification of change : Provided, however, That the Contracting Officer, if he decides that the facts justify such action, may receive...any time prior to final Payment under this contract. Failure to agree to any adjustment shall be a dispute concerning a question of fact within the meaning...
Full view - About this book

Problems of the Uranium Mining and Milling Industry: Hearings Before the ...

United States. Congress. Joint Committee on Atomic Energy - 1958 - 352 pages
...the Contractor of the notification of change ; provided, however, that the Contracting Officer, if he decides that the facts justify such action, may receive...any time prior to final payment under this contract. Failure to agree to any adjustment shall be a dispute concerning a question of fact within the meaning...
Full view - About this book

Study of the Armed Services Procurement Regulations and Departmental ...

United States. Congress. House. Committee on Armed Services - 1958 - 754 pages
...the Contractor of the notification of change: Provided, however. That the Contracting Officer, if he decides that the facts Justify such action, may receive...any time prior to final payment under this contract. In the event of failure mutually to agree to any adjustment, such adjustment, shall be determined by...
Full view - About this book

Problems of the Uranium Mining and Milling Industry: Hearings Before the ...

United States. Congress. Joint Committee on Atomic Energy - 1958 - 346 pages
...the Contractor of the notification of change ; provided, however, that the Contracting Officer, if he decides that the facts justify such action, may receive...any time prior to final payment under this contract. Failure to agree to any adjustment shall be a dispute concerning a question of fact within the meaning...
Full view - About this book

Progress of Atlas and Polaris Missiles: Hearings Before the Committee on ...

United States. Congress. House. Committee on Science and Astronautics - 1959 - 204 pages
...the Contractorof the notification of change; provided, however, that the Contracting Officer, if he decides that the facts justify such action, may receive...any time prior to final payment under this contract. Failure to agree to any adjustment shall be a dispute concerning a question of fact within the meaning...
Full view - About this book

Committee Prints

United States. Congress. Senate. Committee on the Judiciary - 1959 - 1296 pages
...the Contractor of the notification of change; provided, however, that the Contracting Officer, if he mpor x Failure to agree to any adjustment shall be a dispute concerning a question of fact within the meaning...
Full view - About this book

Progress of Atlas and Polaris Missiles: Hearings Before the Committee on ...

United States. Congress. House. Committee on Science and Astronautics - 1959 - 198 pages
...Contractor of the notification of change; provided, however, that the Contracting Officer, if he decide« that the facts Justify such action, may receive and...any time prior to final payment under this contract. Failure to agree to any adjustment «hall be a dispute concerning a question of fact within the meaning...
Full view - About this book

Hearings

United States. Congress. House. Committee on Science and Astronautics - 1959 - 1140 pages
...the Contractor of the notification of change; provided, however, that the Contracting Officer, if he decides that the facts justify such action, may receive...claim asserted at any time prior to final payment tinder this contract. Failure to agree to any adjustment shall be a dispute concerning a question of...
Full view - About this book