" That the right of the contractor to proceed shall not be terminated or the contractor charged with liquidated damages because of any delays in the completion of the work due to unforeseeable causes beyond the control and without the fault or negligence... "
Code of Federal Regulations: Containing a Codification of Documents of ... - Page 405
1955
Full view - About this book

Cases Decided in the Court of Claims of the United States, Volume 110

United States. Court of Claims - 1948 - 818 pages
...expense thereof, except damages to the work due to unforeseeable causes beyond the control of and without fault or negligence of the contractor, including but...God or of the public enemy, acts of the Government, slides found by the engineer to have been unavoidable, * * * Measurement of Quantities. — All work...
Full view - About this book

Decisions of the Comptroller General of the United States, Volume 27

United States. General Accounting Office - 1948 - 938 pages
...making deliveries is due to unforeseeable causes beyond the control and without the fault or neg ligence of the contractor. Including but not restricted to...God or of the public enemy, acts of the Government, fires, floods, epidemics, quarantine restrictions, strikes, freight embargoes, unusually severe weather,...
Full view - About this book

Code of Federal Regulations: Containing a Codification of Documents of ...

1949 - 738 pages
...shall not be terminated or the contractor charged with liquidated damages because of any delays in the completion of the work due to unforeseeable causes...God, or of the public enemy, acts of the Government, acts of another contractor in the performance of a contract with the Government, fires, floods, epidemics,...
Full view - About this book

The Code of Federal Regulations of the United States of America

1972 - 914 pages
...performance of the work shall not be terminated for default because of any delays In the completion of work due to unforeseeable causes beyond the control...God. or of the public enemy, acts of the Government in either its soverign or contractual capacity, acts of another contractor in the performance of a...
Full view - About this book

Service of Supply: Outline of a Training Course for Officers and Employees ...

United States. Bureau of Federal Supply - 1949 - 226 pages
...in the open market or under other contracts when the delay of the contractor in making deliveries is due to unforeseeable causes beyond the control and...God or of the public enemy, acts of the Government, fires, floods, epidemics, quarantine restrictions, strikes, freight embargoes, unusually severe weather,...
Full view - About this book

The Code of Federal Regulations of the United States of America

1967 - 686 pages
...performance of the work shall not be terminated for default because of any delays in the completion of work due to unforeseeable causes beyond the control...restricted to, acts of God, or of the public enemy, acts the Government in either its sovereign or contractual capacity, acts of another contractor in the performance...
Full view - About this book

The Code of Federal Regulations of the United States of America

1970 - 788 pages
...performance of the work shall not be terminated for default because of any delays in the completion of work due to unforeseeable causes beyond the control...including, but not restricted to, acts of God, or the public enemy, acts of the Government In either its sovereign or contractual capacity, acts of another...
Full view - About this book

The Code of Federal Regulations of the United States of America

1977 - 708 pages
...performance of the work shall not be terminated for default because of any delays in the completion of work due to unforeseeable causes beyond the control...including, but not restricted to, acts of God, or the public enemy, acts of the Government in either its sovereign or contractual capacity, acts of another...
Full view - About this book

The Code of Federal Regulations of the United States of America

1949 - 564 pages
...contractor shall not be charged with liquidated damages or any excess cost when the delay in delivery Is due to unforeseeable causes beyond the control and...contractor, Including, but not restricted to, acts of God or the public enemy, acts of the Government, fires, floods, epidemics, quarantine restrictions, strikes,...
Full view - About this book

Code of Federal Regulations: Containing a Codification of Documents of ...

1949 - 906 pages
...that the contractor shall have given Immediate notice thereof he shall not be liable when the delay is due to unforeseeable causes beyond the control and...contractor, Including but not restricted to acts of God, acts of the Government, acts of the public enemy, fires, floods, epidemics, quarantine restrictions,...