Construction ContractsPractising Law Institute, 1975 - 328 pages |
From inside the book
Results 1-3 of 43
Page 154
... resulting from uncontrollable forces . The term uncontrollable forces being deemed for the purpose of this contract to ... result- ing from such uncontrollable forces shall extend the completion dates correspondingly , provided that such ...
... resulting from uncontrollable forces . The term uncontrollable forces being deemed for the purpose of this contract to ... result- ing from such uncontrollable forces shall extend the completion dates correspondingly , provided that such ...
Page 263
... result of the breach of contract . In many cases , the expert is able to assign specific quantitative values to such factors as overtime , inefficiency , over - manning in efficiency loss ( i.e. , your client simply puts too many people ...
... result of the breach of contract . In many cases , the expert is able to assign specific quantitative values to such factors as overtime , inefficiency , over - manning in efficiency loss ( i.e. , your client simply puts too many people ...
Page 283
... result in itself , although certainly not a nega- tive result , is not necessarily the most just for the parties involved . C. Arbitration In those states where modern arbitration statutes have been enacted the machinery exists to ...
... result in itself , although certainly not a nega- tive result , is not necessarily the most just for the parties involved . C. Arbitration In those states where modern arbitration statutes have been enacted the machinery exists to ...
Contents
Practical Problems and Legal Trouble Spots | 31 |
Planning to Avoid Construction Litigation | 49 |
I | 65 |
Copyright | |
7 other sections not shown
Common terms and phrases
8th Cir A.I.A. general conditions accepted agreement amount approval arbi Archi Architect Article award bid shopping bidder Board bond breach of contract Cal.Rptr cause claims Classroom Building clause construction contract CONSTRUCTION LITIGATION construction manager consumer Contract Documents Contractor Corp cost court defects disputes Dist drawings and specifications engineer equipment expense fact failure Federal Flan Floor Plan furnished Ground Floor indemnity installation Insurance jury liability lien limited liquidated damages materials medical malpractice ment Minn negligence owner panel parties payment performance Peter Kiewit Sons Pima County Plan East Wing plans and specifications problems reasonable remedy responsible Restatement of Contracts result rules schedule Sept shop drawings Small Claims Court standard statutes strict liability subcontractor submitted Supp suppliers surety tect temporary tion tractor trial United warranty West Wing