... performance by the promisor impossible occurs subsequent to the formation of the contract.1 / In the construction field many unanticipated problems can develop which will render performance temporarily or permanently impossible . The ...
... performance by the promisor impossible occurs subsequent to the formation of the contract.1 / In the construction field many unanticipated problems can develop which will render performance temporarily or permanently impossible . The ...
Page 101
... Performance is excused or discharged when prevented by operation of law . Cal . Civil Code Section 1511 ( 1 ) ; Collins Hotel Company v . Collins , 4 C.A. 397 , 88 P 292 ( 1906 ) ( Change in City ordinance preventing construc- tion of ...
... Performance is excused or discharged when prevented by operation of law . Cal . Civil Code Section 1511 ( 1 ) ; Collins Hotel Company v . Collins , 4 C.A. 397 , 88 P 292 ( 1906 ) ( Change in City ordinance preventing construc- tion of ...
Page 196
... performance and shall also furnish such report from time to time during performance if the Contractor is then in default . LAWS AND REGULATIONS : Attention of bidders is called to the existance of statutes and regulations relative to ...
... performance and shall also furnish such report from time to time during performance if the Contractor is then in default . LAWS AND REGULATIONS : Attention of bidders is called to the existance of statutes and regulations relative to ...
Contents
Practical Problems and Legal Trouble Spots | 31 |
Planning to Avoid Construction Litigation | 49 |
I | 65 |
Copyright | |
7 other sections not shown
Common terms and phrases
8th Cir A.I.A. general conditions accepted agreement amount approval arbi Archi Architect Article award bid shopping bidder Board bond breach of contract Cal.Rptr cause claims Classroom Building clause construction contract CONSTRUCTION LITIGATION construction manager consumer Contract Documents Contractor Corp cost court defects disputes Dist drawings and specifications engineer equipment expense fact failure Federal Flan Floor Plan furnished Ground Floor indemnity installation Insurance jury liability lien limited liquidated damages materials medical malpractice ment Minn negligence owner panel parties payment performance Peter Kiewit Sons Pima County Plan East Wing plans and specifications problems reasonable remedy responsible Restatement of Contracts result rules schedule Sept shop drawings Small Claims Court standard statutes strict liability subcontractor submitted Supp suppliers surety tect temporary tion tractor trial United warranty West Wing