Construction ContractsPractising Law Institute, 1975 - 328 pages |
From inside the book
Results 1-3 of 51
Page 25
D. Payment for Basic Services - conditioned upon compliance with all contractual obligations 1 . Payment in full upon completion only for minor projects 2. Progress payments with retainage procedure a . b . C. - used - usual Payment ...
D. Payment for Basic Services - conditioned upon compliance with all contractual obligations 1 . Payment in full upon completion only for minor projects 2. Progress payments with retainage procedure a . b . C. - used - usual Payment ...
Page 26
... payment provisions ( Art . 9 ) but in miscellan- eous provisions ( Paragraph 7.9.1 ) 3 . Final payment - a . b . c . d . e . AIA A - 201 , Paragraph 9.7 Certificate of Substantial Completion prepared by architect - assigns re ...
... payment provisions ( Art . 9 ) but in miscellan- eous provisions ( Paragraph 7.9.1 ) 3 . Final payment - a . b . c . d . e . AIA A - 201 , Paragraph 9.7 Certificate of Substantial Completion prepared by architect - assigns re ...
Page 221
... PAYMENT : The Contractor shall sub- mit to the Architect an application for each pay- ment , and if required , receipts or other vouchers , showing his payments for materials and labor , includ- ing payments to Sub - Contractor . Such ...
... PAYMENT : The Contractor shall sub- mit to the Architect an application for each pay- ment , and if required , receipts or other vouchers , showing his payments for materials and labor , includ- ing payments to Sub - Contractor . Such ...
Contents
Practical Problems and Legal Trouble Spots | 31 |
21 | 40 |
A Safeguards in Specifying | 53 |
Copyright | |
10 other sections not shown
Common terms and phrases
8th Cir A.I.A. general conditions accepted agreement amount approval arbi Archi Architect Article award bid shopping bidder Board bond breach of contract Cal.Rptr cause claims Classroom Building clause construction contract CONSTRUCTION LITIGATION construction manager consumer Contract Documents Contractor Corp cost court defects disputes Dist drawings and specifications engineer equipment expense fact failure Federal Flan Floor Plan furnished Ground Floor indemnity installation Insurance jury liability lien limited liquidated damages materials medical malpractice ment Minn negligence owner panel parties payment performance Peter Kiewit Sons Pima County Plan East Wing plans and specifications problems reasonable remedy responsible Restatement of Contracts result rules schedule Sept shop drawings Small Claims Court standard statutes strict liability subcontractor submitted Supp suppliers surety tect temporary tion tractor trial United warranty West Wing