Page 45
... completion and " punchlist " ( list of items to be completed ) , but does not define " substantial.completion . " It is difficult to state what the terms " substantial performance , " " substan- tial compliance " or " substantial ...
... completion and " punchlist " ( list of items to be completed ) , but does not define " substantial.completion . " It is difficult to state what the terms " substantial performance , " " substan- tial compliance " or " substantial ...
Page 163
... completion in Article 4 hereof , or within the times to which such completion may have been extended , the Contractor must pay to the Authority the sums stated below for each and every cal- endar day that the time consumed in completing ...
... completion in Article 4 hereof , or within the times to which such completion may have been extended , the Contractor must pay to the Authority the sums stated below for each and every cal- endar day that the time consumed in completing ...
Page 196
... COMPLETION : With his executed contract , the successful bidder must deliver to the Board of Education an executed performance and completion bond with labor and materialmen's clauses in form meeting the Board's approval , in amount not ...
... COMPLETION : With his executed contract , the successful bidder must deliver to the Board of Education an executed performance and completion bond with labor and materialmen's clauses in form meeting the Board's approval , in amount not ...
Contents
Practical Problems and Legal Trouble Spots | 31 |
Planning to Avoid Construction Litigation | 49 |
I | 65 |
Copyright | |
7 other sections not shown
Common terms and phrases
8th Cir A.I.A. general conditions accepted agreement amount approval arbi Archi Architect Article award bid shopping bidder Board bond breach of contract Cal.Rptr cause claims Classroom Building clause construction contract CONSTRUCTION LITIGATION construction manager consumer Contract Documents Contractor Corp cost court defects disputes Dist drawings and specifications engineer equipment expense fact failure Federal Flan Floor Plan furnished Ground Floor indemnity installation Insurance jury liability lien limited liquidated damages materials medical malpractice ment Minn negligence owner panel parties payment performance Peter Kiewit Sons Pima County Plan East Wing plans and specifications problems reasonable remedy responsible Restatement of Contracts result rules schedule Sept shop drawings Small Claims Court standard statutes strict liability subcontractor submitted Supp suppliers surety tect temporary tion tractor trial United warranty West Wing