Search Images Maps Play YouTube News Gmail Drive More »
Sign in
Books Books
" If no schedule or agreement stating the dates upon which drawings shall be furnished is made, then no claim for delay shall be allowed on account of failure to furnish drawings until two weeks after demand for such drawings and not then unless such claim... "
Official Proceedings of the ... Annual Convention - Page 533
by American Society for Municipal Improvements. Convention - 1926
Full view - About this book

The Law of Architecture and Building: A Consideration of the Mutual Rights ...

Clinton Hamlin Blake - 1916 - 360 pages
...is made under Art. 3, no claim for delay shall be allowed on account of failure to furnish drawings until two weeks after demand for such drawings and not then unless such claim be reasonable. Art. 36. Owner's Right to Do Work.—If the Contractor should neglect to prosecute the work properly...
Full view - About this book

Cyclopedia of Architecture, Carpentry, and Building: A General ..., Volume 6

1917 - 550 pages
...is made under Art. 3, no claim for delay shall be allowed on account of failure to furnish drawings until two weeks after demand for such drawings, and not then unless such claim be reasonable. Art. 36. Owner's Right to Do Work. — If the Contractor should neglect to prosecute the work properly...
Full view - About this book

Business Law for Engineers

Calvin Frank Allen - 1917 - 472 pages
...is made under Art. 3, no claim for delay shall be allowed on account of failure to furnish drawings until two weeks after demand for such drawings and not then unless such claim be reasonable. Art. 36. Owner's Right to Do Work. — If the Contractor should neglect to prosecute the work properly...
Full view - About this book

Business Law for Engineers

Calvin Frank Allen - 1917 - 468 pages
...is made under Art. 3, no claim for delay shall be allowed on account of failure to furnish drawings until two weeks after demand for such drawings and not then unless such claim be reasonable. Art. 36. Owner's Right to Do Work. — If the Contractor should neglect to prosecute the work properly...
Full view - About this book

Business Law for Engineers

Calvin Frank Allen - 1919 - 490 pages
...is made under Art. 3, no claim for delay shall be allowed on account of failure to furnish drawings until two weeks after demand for such drawings and...recovery of damages for delay by either party under Article 39 or other provisions in the contract documents. however, that the Architect shall approve...
Full view - About this book

Business Law for Engineers

Calvin Frank Allen - 1919 - 476 pages
...is made under Art. 3, no claim for delay shall be allowed on account of failure to furnish drawings until two weeks after demand for such drawings and...recovery of damages for delay by either party under Article 39 or other provisions in the contract documents. however, that the Architect shall approve...
Full view - About this book

Business Law for Engineers

Calvin Frank Allen - 1919 - 486 pages
...is made under Art. 3, no claim for delay shall be allowed on account of failure to furnish drawings until two weeks after demand for such drawings and...recovery of damages for delay by either party under Article 39 or other provisions in the contract documents. Art. 36. Owner's Right to Do Work. — If...
Full view - About this book

Carpentry and Contracting: A Practical Reference Work on Carpentry ..., Volume 5

1919 - 476 pages
...is made under Art. 3, no claim for delay shall be allowed on account of failure to furnish drawings until two weeks after demand for such drawings, and not then unless such claim be reasonable. Art. 36. Owner's Right to Do Work.— If the Contractor should neglect to prosecute the work properly...
Full view - About this book

The Handbook of Architectural Practice

American Institute of Architects - 1920 - 208 pages
...is made under Art. 3, no claim for delay shall be allowed on account of failure to furnish drawings until two weeks after demand for such drawings and...recovery of damages [for delay by either party under article 39 or other provisions in the contract documents. Art. 36. Owner's Right to Do Work.— If...
Full view - About this book

The Handbook of Architectural Practice

American Institute of Architects - 1920 - 212 pages
...is made under Art. 3, no claim for delay shall be allowed on account of failure to furnish drawings until two weeks after demand for such drawings and not then unless such claim he reasonable. This article does not exclude the recovery of damages [for. delay by either party under...
Full view - About this book




  1. My library
  2. Help
  3. Advanced Book Search
  4. Download EPUB
  5. Download PDF