ORDER OF COMPLETION; USE OF COMPLETED PORTIONS. The Contractor shall complete any portion or portions of the work in such order of time as the Engineer may require. The Company shall have the right to take possession of and use any completed or partially... Official Proceedings of the ... Annual Convention - Page 535by American Society for Municipal Improvements. Convention - 1926Full view - About this book
| American Electric Railway Association - 1920 - 514 pages
...possession and use shall not be deemed an acceptance of the work as taken or used, or any part thereof. (c) If such prior use increases the cost of or delays the work, the Contractor will be entitled to such extra compensation or extension of time, or both, as the Engineer may determine.... | |
| American Railway Engineering Association - 1914 - 1224 pages
...Company shall have the right to take possession of and use any completed or partially completed portions of the work, notwithstanding the time for completing...increases the cost of or delays the work, the Contractor will be entitled to such extra compensation, or extension of time, or both, as the Chief Engineer may... | |
| American Electric Railway Association - 1914 - 634 pages
...Owner shall have the right to take possession of and use any completed or partially completed portions of the work, notwithstanding the time for completing the entire work or such portion may not have expired ; but such taking possession and use shall not be deemed an acceptance... | |
| Calvin Frank Allen - 1917 - 468 pages
...Company shall have the right to take possession of and use any completed or partially completed portions of the work notwithstanding the time for completing...increases the cost of or delays the work, the Contractor will be entitled to such extra compensation, or extension of time, or both, as the Chief Engineer may... | |
| Calvin Frank Allen - 1917 - 472 pages
...Company shall have the right to take possession of and use any completed or partially completed portions of the work notwithstanding the time for completing...increases the cost of or delays the work, the Contractor will be entitled to such extra compensation, or extension of time, or both, as the Chief Engineer may... | |
| Calvin Frank Allen - 1919 - 486 pages
...Company shall have the right to take possession of and use any completed or partially completed portions of the work notwithstanding the time for completing...increases the cost of or delays the work, the Contractor will be entitled to such extra compensation, or extension of time, or both, as the Chief Engineer may... | |
| American Electric Railway Engineering Association - 1922 - 1362 pages
...not have •J?:red; but such taking possession and use shall not be deemed an Wijtance of the work as taken or used, or any part thereof. (:) If such prior...use increases the cost of or delays the work, the Cwtractor will be entitled to such extra compensation or extension rf time, or both, as the Engineer... | |
| Perley F. Walker - 1924 - 380 pages
...Company shall have the right to take possession of and use any completed or partially completed portions of the work, notwithstanding the time for completing...use increases the cost of or delays the work, the Constructor shall be entitled to such extra compensation, or extension of time, or both, as the Chief... | |
| American Water Works Association - 1925 - 882 pages
...Owner shall have the right to take possession of and use any completed or partially completed portions of the work, notwithstanding the time for completing...possession and use shall not be deemed an acceptance of any work not completed in accordance with the Contract Documents. If such prior use increases the cost... | |
| |