" Any claim by the Contractor for adjustment under this clause must be asserted within 30 days from the date of receipt by the Contractor of the notification of change, provided, however, that the Contracting Officer, if he decides that the facts justify... "
Decisions of the Comptroller General of the United States - Page 254
by United States. General Accounting Office - 1973
Full view - About this book

Cases Decided in the United States Court of Claims ... with ..., Volume 145

United States. Court of Claims, Audrey Bernhardt - 1959 - 820 pages
...of whether, under the "Changes" article of the contract, plaintiff can escape the requirement that "Any claim by the contractor for adjustment under...by the contractor of the notification of change," and the requirement that any disputes concerning a question of fact resulting from the change shall...
Full view - About this book

Specifications for Gun Forgings for the United States Army and Navy, August 1918

United States. Army. Ordnance Department. War Department - 1926 - 36 pages
...caliber, two months. (4) All other gun forgings, six weeks. The above-mentioned time allowances shall date from the date of receipt by the contractor of the notification of rejection. If these times of replacement are exceeded the department may grant such extensions as the...
Full view - About this book

Code of Federal Regulations: Containing a Codification of Documents of ...

1964 - 1202 pages
...changed by any such order, an equitable adjustment shall be made in the contract price or delivery schedule, or both, and the contract shall be modified...Contractor of the notification of change: Provided, howevtr. That the Contracting Officer, if he decides that the facts justify such action, may receive...
Full view - About this book

The Code of Federal Regulations of the United States of America

1982 - 536 pages
...an equitable adjustment shall be made in the contract price or delivery schedule, or both, and tha contract shall be modified in writing accordingly....Contractor of the notification of change: Provided, fiou-rrrr. That the Contracting Officer, if he decides that the facts justify such action, may receive...
Full view - About this book

Code of Federal Regulations: Containing a Codification of Documents of ...

1972 - 862 pages
...changed by any such order, an equitable adjustment shall be made In the contract price or delivery schedule, or both, and the contract shall be modified...30 days from the date of receipt by the Contractor of the notlflcatlon of change: Provided, however, That the Contracting Officer, if he decides that...
Full view - About this book

The Code of Federal Regulations of the United States of America

1977 - 944 pages
...paid to the contractor; and (3) In such other provisions of the contract as may be affected, and the contract shall be modified In writing accordingly....receipt by the Contractor of the notification of change: Prodded, however, That the Contracting Officer, It he decides that the facts justify such action, may...
Full view - About this book

Code of Federal Regulations: Containing a Codification of Documents of ...

1973 - 944 pages
...changed by any such order, an equitable adjustment shall be made In the contract price or delivery schedule, or both, and the contract shall be modified...clause must be asserted within 30 days from the date or receipt by the Contractor of the notification of change, provided, however, that the Contracting...
Full view - About this book

The Code of Federal Regulations of the United States of America

1966 - 968 pages
...changed by any such order, an equitable adjustment shall be made In the contract price or delivery schedule, or both, and the contract shall be modified...clause must be asserted within 30 days from the date or receipt by the Contractor of the notification of change, provided, however, that the Contracting...
Full view - About this book

Code of Federal Regulations: Containing a Codification of Documents of ...

1991 - 550 pages
...other provisions of a contract, such as the requirement in the Changes clause of Standard Form 32, that any "claim by the contractor for adjustment under...by the contractor of the notification of change," are considered to be specifically required under the interpretation. (2) Indirect allocation of all...
Full view - About this book

Code of Federal Regulations: Containing a Codification of Documents of ...

1986 - 1072 pages
...changed by any such order, an equitable adjustment shall be made in the contract price or delivery schedule or both and the contract shall be modified...adjustment under this clause must be asserted within 30 calendar days from the date of receipt by the Contractor of the notification of change: Provided, however,...