$25,430.00

Amount (estimated) required for completion of existing project..
Amount that can be proniably expended in fiscal year ending June 30,1891 15,000.00
Submitted in compliance with requirements of sections 2 of river and
harbor acts of 1866 and 1867.

(See Appendix Q 6.)

7. Flint River, Georgia.-Originally the river was only navigable at low water from its mouth up to Bainbridge, and even that portion was narrow, crooked, and dangerous. Above Bainbridge it was very much obstructed by logs, snags, overhanging trees, and rock shoals.

The present project for the improvement of this river was adopted in 1873, and modified in 1880, the object of the original project being to afford a channel 100 feet wide and 3 feet deep at ordinary low water from its mouth up to Albany, Ga., and of the modification to improve for high-water navigation that portion of the river between Albany and Montezuma.

The expenditure up to June 30, 1888, of $113,917.23 has resulted in obtaining a high-water channel from its mouth up to Albany and a lowwater channel of the projected depth from its mouth up to Blue Springs Shoals, about 4 miles below Albany; also a partially completed highwater channel over that portion of the river between Albany and Mon

tezuma.

During the year ending June 30, 1889, $8,446.53 was expended. A channel of the required depth was excavated through Blue Springs Shoals nearly to Albany. On account of the want of plant no work was done above Albany. A new plant, consisting of snag-boat, drilling barge, and dumping flat, has been contracted for, and should be deliv ered on July 10, 1889.

July 1, 1888, amount available, including liabilities outstanding..
Amount appropriated by act of August 11, 1888

July 1, 1889, amount expended during fiscal year, exclusive of liabilities outstanding July 1, 1888.

July 1, 1889, outstanding liabilities

July 1, 1889, amount covered by existing contracts

July 1, 1889, balance available

$3, 112.53 20,000.00

23, 112.53

$8,446.53
634.50
8, 200.00

17, 281.03

5,831.50

62,962.00

(Amount (estimated) required for completion of existing project
Amount that can be profitably expended in fiscal year ending June 30, 1891
Submitted in compliance with requirements of sections 2 of river and
harbor acts of 1866 and 1867.

(See Appendix Q 7.)

30, 000, 00

8. Coosa River, Georgia and Alabama.-The river was originally much obstructed by rock shoals and sand bars between Rome and Greensport, and below Greensport it was not navigable at all on account of such obstructions.

A plan was adopted in 1875 to provide a channel not less than 80 feet wide and 3 feet deep at low water between Rome, Ga., and the Selma, Rome and Dalton Railroad Bridge, an estimated distance of 236 miles, increasing the depth over the lesser rock shoals and over sand and gravel bars by excavation and by works of contraction, and overcoming the more serious obstructions by the construction of locks and dams.

The expenditure up to June 30, 1888, of $461,155.50 had resulted in securing a fair navigable channel from Rome, Ga., to Greensport, Ala., by blasting out the rock shoals and by the construction of wing-dams for clearing out the sand bars. Below Greensport a system of slack

water navigation was provided for by the construction of locks and dams. Three masonry locks, at distances, respectively, of 0.68, 3.86, and 5.24 miles below Greensport, had been nearly completed with their dams, and a fourth lock and dam, 21 miles below Lock No. 3, had been commenced. The completion of the first three locks, with the dam at Lock 4, will give access from Rome, Ga., to the Coosa River coal-fields. During the year ending June 30, 1889, the expenditure of $26,839.84 has resulted in the practical completion of Locks 1, 2, and 3, some modifications in the valves only being required to open them to navigation. The act of August 11, 1888, provided for a survey of the river from Lock 4 to Wetumpka, with estimates for its improvement. This survey is now in progress. Lock 4 will be the first lock in the down-stream navigation should the river be opened to Wetumpka, and it is proposed to increase its dimensions to 52 feet by 322 feet.

The building of Lock 4, with the opening of the river below it to Wetumpka, will provide water transportation from the Coosa River coalfields to the Gulf at Mobile, Alabama, by way of the Alabama River. July 1, 1838, amount available, including liabilities outstanding.. Amount appropriated by act of August 11, 1888..........

$2,544.50 60,000.00

62, 544.50

July 1, 1889, outstanding liabilities

July 1, 1889, amount expended during fiscal year, exclusive of liabilities outstanding July 1, 1888

[blocks in formation]

July 1, 1889, balance available ....

30, 670.78

225,000.00

Amount (estimated) required for completion of existing project...
Amount that can be profitably expended in fiscal year ending June 30, 1891 225,000.00
Submitted in compliance with requirements of sections 2 of river and
harbor acts of 1866 and 1867.

(See Appendix Q 8.)

9. Chattahoochee River, Georgia and Alabama.-The river was originally much obstructed by logs, snags, overhanging trees, and by a number of rock and marl shoals and sand-bars, so that navigation was difficult and dangerous. Steam-boats could only run by daylight, and were then often detained for days by a single obstruction. Very many were lost by striking snags or logs.

The present plan of improvement (adopted in 1873) contemplates a low-water channel 4 feet in depth and 100 feet in width from Columbus, Ga., to Chattahoochee, Fla., a distance of 224 miles, by the removal of snags and other obstructions from the channel and overhanging trees from the banks, by the excavation of rock shoals, and by works of contraction.

Previous to the act of June 18, 1878, $70,000 was appropriated for "Chattahoochee and Flint rivers," but it is not known how the amount was apportioned.

Up to June 30, 1888, $150,134.04 of the appropriations for the Chattahoochee River alone had been expended, and with its share of the combined appropriations had resulted in securing a fair navigable channel between Chattahoochee and Eufaula at all seasons of the year, and between Eufaula and Columbus at all times except during the prevalence of extreme low water. Steam-boats now make regular trips with but few accidents or detentious, running by night as well as by day. The limited annual appropriations for this improvement have not been sufficient to maintain the works of contraction constructed, nor

to extend or modify them as required. The jetties and training walls are in need of much repair.

During the year ending June 30, 1889, $10,507.57 has been expended in maintaining the existing improvement, excavating rock shoals, and in procuring new plant to replace that worn out.

July 1, 1888, amount available, including liabilities outstanding..
Amount appropriated by act of August 11, 1888. .

$2,884. 17 20,000.00

22, 884. 17

July 1, 1889, amount expended during fiscal year, exclusive of liabilities outstanding July 1, 1888.

$10,507.57

July 1, 1889, outstanding liabilities..

729.72

3,400.00

14,637.29

8, 246.88

182.247.66

July 1, 1889, amount covered by existing contracts.

July 1, 1889, balance available......

Amount (estimated) required for completion of existing project...
Amount that can be profitably expended in fiscal year ending June 30, 1891 40,000.00
Submitted in compliance with requirements of sections 2 of river and
harbor acts of 1866 and 1867.

(See Appendix Q 9.)

10. Tallapoosa River, Alabama.-The condition of this river when first examined was such that navigation was entirely suspended at low water, owing to the great accumulation of logs, snags, sunken and fallenin timber, a large number of overhanging trees obstructing the channel, gravel and sand-bars, and at some points reefs of rock crossing the river, thus rendering navigation dangerous if not impracticable. The river presented generally long reaches of fine open navigable water with a width of 200 to 300 feet and a depth of 6 to 12 feet, and when this width was exceeded to any extent shoal water was found with gravel and island bars.

The original project adopted pursuant to an examination and partial survey of this river, made under an act of Congress approved June 14, 1880, contemplated obtaining a navigable channel from the mouth of the river to the foot of the Tallassee Reefs, 2 miles below the town of Tallassee, a distance of 48 miles, with a least depth of 3 feet and a width of 60 feet at low water, by the removal of logs and snags from the channel and of all overhanging timber from the banks where they interfere with navigation, by cutting through the soft rock that obstructed the river at several points, by contracting the channel at various shoal places with dams, jetties, and dikes, and also building such shore protection as might be found necessary. The present project, approved September 13, 1888, provides for a detailed survey of this river with permanent stations and bench-marks at intervals of about 1 mile, in connection with the original project, but has not yet been made on account of insufficiency of funds.

The expenditure of $30,700.86, up to June 30, 1888, resulted in clearing out all logs and snags from the river channel, and in improving one of the rock-reefs, so as to admit of navigation at a moderate stage of water for a distance of 48 miles from the mouth of the river.

The amount expended during the fiscal year ending June 30, 1889, was $5,136.48, and resulted in clearing the channel from its junction with the Coosa to the foot of Tallassee Reefs, a distance of 48 miles, of all snags and logs brought in during the winter freshets, and the removal of a considerable amount of overhanging timber from the banks, rendering the river navigable for small boats of 20-inch draught during the entire year.

July 1, 1888, amount available, including liabilities outstanding.
Amount appropriated by act of August 11, 1888

July 1, 1889, amount expended during fiscal year, exclusive of liabilities outstanding July 1, 1888.

July 1, 1889, outstanding liabilities

July 1, 1889, balance available

$1,817.14 7,500.00

9, 317. 14

$5, 136.48
387.52

5,524.00

3,793. 14

Amount that can be profitably expended in fiscal year ending June 30, 1891, for maintenance and survey..

Submitted in compliance with requirements of sections 2 of river and harbor acts of 1866 and 1867.

(See Appendix Q 10.)

10,000.00

11. Cahaba River, Alabama.-Under the act of Congress approved June 23, 1874, and an act approved June 14, 1880, examinations and a partial survey of this river were made in 1874 and iu 1880, pursuant to which the present plan of improvement was adopted. This contemplates a channel 60 feet wide and 3 feet deep at low water from the mouth of the river to Centreville, Ala., a distance of 88 miles, by the removal of logs and snags from the channel, cutting overhanging trees from the banks, protecting caving banks from further erosion, removing rock-reefs, gravel-bars, and sand-bars, by excavation, and by works of contraction and widening the narrow portions of the river at certain specified points.

The expenditure up to June 30, 1888, of $29,698.15 had resulted in clearing the river channel of logs and snags, and removing overhanging trees from the mouth of the river to Centreville, and in maintaining this degree of improvement up to close of the fiscal year ending June 30, 1886. Since that time no work has been done because of a proviso in the river and harbor act of August 5, 1886, that "no part of said sum ($7,500 appropriated for this work) shall be expended until the officer in charge shall have reported that the railroad and other bridges across said river have been provided with good and suf ficient draw openings." These bridges continue to obstruct the navigation of the river, not having been provided with draw openings. The working plant of the Cahaba River has been transferred to the Escambia and Conecuh improvement.

July 1, 1888, amount available....
July 1, 1889, balance available..

$7,801.85

7,801.85

157,500.00

Amount (estimated) required for completion of existing project...
Amount that can be profitably expended in fiscal year ending June 30, 1891 20,000.00
Submitted in compliance with requirements of sections 2 of river and
harbor acts of 1866 and 1867.

(See Appendix Q 11.)

12. Alabama River, Alabama.-The original condition of the river channel during the low-water season was such that commerce was much restricted, the smallest class of steam-boats only running, navigation being difficult and dangerous. These restrictions were caused by the innumerable bars, shoals, reefs, and collection of sunken logs and snags, at many of which points the low-water depth was reduced to 34 feet, and at some points to 24 feet. The width of the channel varies with the width of the river. The general width of the river from the mouth of the Coosa down to Gainestown ranges from 500 to 600 feet; below that point the width increases to 700 and 800 feet; wherever these widths

are exceeded to any extent are found the bars, shoals, and reefs. In the open reaches of the river ample water is found. That portion below the Cut-Off, 20 miles in length, was absolutely inaccessible during low water, and all the landings situated thereupon were deprived of reliable service during that season.

The plan of improvement adopted pursuant to an examination and partial survey of this river, made under an act of Congress approved March 3, 1875, contemplated obtaining a channel 200 feet in width and 4 feet in depth at low water from the mouth of the Alabama, 50 miles above Mobile, to Wetumpka, Ala., a distance of 387 miles, by the removal of snags, logs, etc., from the channel, cutting overhanging trees from the banks, protecting caving banks from further erosion, removing rock-reefs, gravel and sand-bars by blasting, dredging, and works of contraction at certain specified points of the river. The present proj ect, approved September 13, 1888, provides for a detailed survey of this river, with permanent stations and bench marks at intervals of about 1 mile, in connection with the original project, but has not yet been made on account of insufficiency of funds.

The expenditure of $142,712.56, up to June 30, 1888, resulted in clearing the river of all dangerous snags, overhanging timber, in the improvement of the worst bars, in opening 20 miles of the river below the Cut-Off, before inaccessible during low water, in an increased safety to navigation, greater regularity and reduction in time of trips, and enabling boats to carry larger loads.

During the year ending June 30, 1889, $8,882.52, was expended in maintaining the existing improvements.

July 1, 1838, amount available, including liabilities outstanding.
Amount appropriated by act of August 11, 1838.

[blocks in formation]

July 1, 1889, amount expended during fiscal year, exclusive of liabilities outstanding July 1, 1888

July 1, 1889, outstanding liabilities

$8,882.52
891.41

9,773.93

12, 513. 51

July 1, 1889, balance available....

Amount (estimated) required for completion of existing project (subject to revision)..

200,000.00

Amount that can be profitably expended in fiscal year ending June 30, 1891 40,000.00 Submitted in compliance with requirements of sections 2 of river and harbor acts of 1866, and 1867.

(See Appendix Q 12.)

13. Removal of sunken vessels or craft obstructing or endangering navigation.-A fragment of wreckage from the middle-ground entrance to Pensacola Harbor was removed by the contractor, Mr. William Hughes, of Warrington, Fla. The work was completed in November, 1888. (See Appendix Q 13.)

EXAMINATIONS AND SURVEYS FOR IMPROVEMENT, TO COMPLY WITH REQUIREMENTS OF THE RIVER AND HARBOR ACT OF AUGUST 5,

1886.

The river and harbor act of August 5, 1886, provided for the resurvey of outer and inner bars at Pensacola, Florida, and the following paragraph in reference thereto is quoted from my annual report for the fiscal year ending June 30, 1888:

Under the provisions of section 6 of the river and harbor act approved August 5, 1886, Captain Hoxie was charged with resurvey of outer and inner bars at Pensacola, Fla., which has not yet been completed owing to insufficient amount of the allotment