Art. 3, no claim for delay shall be allowed on account of failure to furnish drawings until two weeks after demand for such drawings and not then unless such claim be reasonable. This Article does not exclude the recovery of damages for delay by either... The Architect's Law Manual - Page 205by Clinton H. Blake (Jr) - 1924 - 253 pagesFull view - About this book
| Clinton Hamlin Blake - 1916 - 360 pages
...the work, or by strikes, lockouts, fire, unavoidable casualties or any causes beyond the Contractor's control, or by delay authorized by the Architect pending...drawings and not then unless such claim be reasonable. Art. 36. Owner's Right to Do Work.—If the Contractor should neglect to prosecute the work properly... | |
| Calvin Frank Allen - 1917 - 468 pages
...the work, or by strikes, lockouts, fire, unavoidable casualties or any causes beyond the Contractor's control, or by delay authorized by the Architect pending...drawings and not then unless such claim be reasonable. Art. 36. Owner's Right to Do Work. — If the Contractor should neglect to prosecute the work properly... | |
| Calvin Frank Allen - 1917 - 472 pages
...the work, or by strikes, lockouts, fire, unavoidable casualties or any causes beyond the Contractor's control, or by delay authorized by the Architect pending...drawings and not then unless such claim be reasonable. Art. 36. Owner's Right to Do Work. — If the Contractor should neglect to prosecute the work properly... | |
| 1917 - 550 pages
...the work, or by strikes, lockouts, fire, unavoidable casualties or any causes beyond the Contractor's control, or by delay authorized by the Architect pending...drawings, and not then unless such claim be reasonable. Art. 36. Owner's Right to Do Work. — If the Contractor should neglect to prosecute the work properly... | |
| Calvin Frank Allen - 1919 - 486 pages
...fire, unusual delay by common carriers, unavoidable casualties or any causes beyond the Contractor's control, or by delay authorized by the Architect pending...provisions in the contract documents. Art. 36. Owner's Right to Do Work. — If the Contractor should neglect to prosecute the work properly or fail to perform... | |
| Calvin Frank Allen - 1919 - 490 pages
...fire, unusual delay by common carriers, unavoidable casualties or any causes beyond the Contractor's control, or by delay authorized by the Architect pending...39 or other provisions in the contract documents. however, that the Architect shall approve both such action and the amount charged to the Contractor.... | |
| Calvin Frank Allen - 1919 - 476 pages
...fire, unusual delay by common carriers, unavoidable casualties or any causes beyond the Contractor's control, or by delay authorized by the Architect pending...39 or other provisions in the contract documents. however, that the Architect shall approve both such action and the amount charged to the Contractor.... | |
| 1919 - 476 pages
...the work, or by strikes, lockouts, fire, unavoidable casualties or any causes beyond the Contractor's control, or by delay authorized by the Architect pending...drawings, and not then unless such claim be reasonable. Art. 36. Owner's Right to Do Work.— If the Contractor should neglect to prosecute the work properly... | |
| American Institute of Architects - 1920 - 208 pages
...fire, unusual delay by common carriers, unavoidable casualties or any causes beyond the Contractor's control, or by delay authorized by the Architect pending...provisions in the contract documents. Art. 36. Owner's Right to Do Work.— If the Contractor should neglect to prosecute the work properly or fail to perform... | |
| American Institute of Architects - 1920 - 212 pages
...writing to the Architect. In the case of a continuing cause of delay, only one claim is necessary. _ If no schedule is made under Art. 3, no claim for...demand for such drawings and not then unless such claim he reasonable. This article does not exclude the recovery of damages [for. delay by either party under... | |
| |