Page 70
... complete , or at least sub- stantial , performance by one party is a prerequisite to his right to compel performance ... completing the work is entitled to compensation for materials supplied and for that portion of the work done ...
... complete , or at least sub- stantial , performance by one party is a prerequisite to his right to compel performance ... completing the work is entitled to compensation for materials supplied and for that portion of the work done ...
Page 151
... complete superstructure , including asphalt - paved movable span , towers , counterweights , power equipment ... complete abutments with pavements 3. Two ( 2 ) complete approaches with pavements 4. Complete removal of the substructure ...
... complete superstructure , including asphalt - paved movable span , towers , counterweights , power equipment ... complete abutments with pavements 3. Two ( 2 ) complete approaches with pavements 4. Complete removal of the substructure ...
Page 413
... Complete the Contract in accordance with its terms and conditions , or " ( 2 ) Obtain a bid or bids for submission to Owner for completing the Contract in accordance with its terms and conditions , and upon determination by Owner and ...
... Complete the Contract in accordance with its terms and conditions , or " ( 2 ) Obtain a bid or bids for submission to Owner for completing the Contract in accordance with its terms and conditions , and upon determination by Owner and ...
Other editions - View all
Common terms and phrases
acceptance accord and satisfaction action actual agent agreement application approval arbitration architect assume ASTM authority basis bid price bid shopping bidder bond breach building cause circumstances claim clause cofferdams compensation complete concrete condition consideration construction contracts contract clauses contract documents contract drawings contractor contributory negligence corporation cost court damages defects defendant duty enforce engineer engineer's entitled equipment erection estimate example excavation extra furnished illustration injury intended interest involved liability liquidated damages lump-sum materials matter means ment necessary negligence obligation operations owner particular partner partnership party patent payment performance performance bond person plaintiff plans prepared principal promise promisor proposal form quantities real property reasonable regarding responsible result rule specifications statute steel stipulated structure subcontractor tion tort tract tractor ultra vires unit prices unit-price contract unless West Virginia Turnpike witness workmanship