Professional Construction Management |
From inside the book
Results 1-3 of 29
Page 42
... from entire projects to specialization in one or more technical or process - oriented major portions of typical installations . ... coupled with parallel development of in - house capabilities for the level portion of the workload .
... from entire projects to specialization in one or more technical or process - oriented major portions of typical installations . ... coupled with parallel development of in - house capabilities for the level portion of the workload .
Page 154
The lower portion simplifies the life of a project to a three - activity bar chart consisting of ( 1 ) engineering and design , ( 2 ) procurement and construction , and ( 3 ) utilization or operation . The upper portion plots two main ...
The lower portion simplifies the life of a project to a three - activity bar chart consisting of ( 1 ) engineering and design , ( 2 ) procurement and construction , and ( 3 ) utilization or operation . The upper portion plots two main ...
Page 395
5.3 The Date of Substantial Completion of the Project or a designated portion thereof is the date when construction is sufficiently complete in accordance with the Drawings and Specifications so the Owner can occupy or utilize the ...
5.3 The Date of Substantial Completion of the Project or a designated portion thereof is the date when construction is sufficiently complete in accordance with the Drawings and Specifications so the Owner can occupy or utilize the ...
What people are saying - Write a review
We haven't found any reviews in the usual places.
Contents
Constructions Future 3 5 Cz | 6 |
What Is Professional Construction Management? | 13 |
MANAGEMENT IN PRACTICE | 15 |
Copyright | |
20 other sections not shown
Other editions - View all
Common terms and phrases
activities actual additional Agreement alternative amount applicable approach approval Architect award basic bidders budget building changes Chapter chart compared completion concepts concrete considerations contract contractor cost detailed determine developed direct documents drawings economic effect engineering equipment estimate evaluation example facilities factors field Figure finish firms important individual industry inspection involved knowledge labor major materials methods needed negotiated objectives obtain operations organization overall owner packages payment percent performance period phase planning plant practices preliminary prepared problems procedures procurement productivity professional construction manager progress proposed quantities reasonable reports responsibilities safety savings schedule scope selection separate shows specifications standard Structural subcontractors summary testing tion Trade traditional unassigned unit utilities value engineering warehouse