Professional Construction Management |
From inside the book
Results 1-3 of 80
Page 163
6 To deliver the information to them in time for consideration and decision making so that , if necessary , corrective action may be taken on those operations that generated the data in the first place . Project Planning and Control : A ...
6 To deliver the information to them in time for consideration and decision making so that , if necessary , corrective action may be taken on those operations that generated the data in the first place . Project Planning and Control : A ...
Page 167
The concrete superintendent should have reports focusing on concrete operations . The project manager should have summary reports as well as logically coordinated detail reports to back them up . Variances Reports for control purposes ...
The concrete superintendent should have reports focusing on concrete operations . The project manager should have summary reports as well as logically coordinated detail reports to back them up . Variances Reports for control purposes ...
Page 283
It must relate especially closely to the project schedule for operations and resources . One approach would be simply to merge the procurement activities with the operations activities , say on a CPM diagram .
It must relate especially closely to the project schedule for operations and resources . One approach would be simply to merge the procurement activities with the operations activities , say on a CPM diagram .
What people are saying - Write a review
We haven't found any reviews in the usual places.
Contents
Constructions Future 3 5 Cz | 6 |
What Is Professional Construction Management? | 13 |
MANAGEMENT IN PRACTICE | 15 |
Copyright | |
20 other sections not shown
Other editions - View all
Common terms and phrases
activities actual additional Agreement alternative amount applicable approach approval Architect award basic bidders budget building changes Chapter chart compared completion concepts concrete considerations contract contractor cost detailed determine developed direct documents drawings economic effect engineering equipment estimate evaluation example facilities factors field Figure finish firms important individual industry inspection involved knowledge labor major materials methods needed negotiated objectives obtain operations organization overall owner packages payment percent performance period phase planning plant practices preliminary prepared problems procedures procurement productivity professional construction manager progress proposed quantities reasonable reports responsibilities safety savings schedule scope selection separate shows specifications standard Structural subcontractors summary testing tion Trade traditional unassigned unit utilities value engineering warehouse