Professional Construction Management |
From inside the book
Results 1-3 of 51
Page 204
1.0 0.9 50 - hour week 0.8 Productivity relative to 40 - hour week Points of no return 0.7 60 - hour week 0.6 1 1 1 1 I 1 0.5 0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 Week ( a ) Cumulative effect of overtime on productivity 2.5 60 - hour ...
1.0 0.9 50 - hour week 0.8 Productivity relative to 40 - hour week Points of no return 0.7 60 - hour week 0.6 1 1 1 1 I 1 0.5 0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 Week ( a ) Cumulative effect of overtime on productivity 2.5 60 - hour ...
Page 243
The Effects of Changes The effects of changes can be subdivided into three main categories : 1 Direct costs 2 ... In concept , the delay in an activity in a CPM network could be propagated through its successors to assess the effect .
The Effects of Changes The effects of changes can be subdivided into three main categories : 1 Direct costs 2 ... In concept , the delay in an activity in a CPM network could be propagated through its successors to assess the effect .
Page 343
A disturbing finding was that having or not having safety meetings seemed to have no effect on the lost - time or minor - accident rate . This is not to imply that all job safety meetings are ineffective .
A disturbing finding was that having or not having safety meetings seemed to have no effect on the lost - time or minor - accident rate . This is not to imply that all job safety meetings are ineffective .
What people are saying - Write a review
We haven't found any reviews in the usual places.
Contents
Constructions Future 3 5 Cz | 6 |
What Is Professional Construction Management? | 13 |
MANAGEMENT IN PRACTICE | 15 |
Copyright | |
20 other sections not shown
Other editions - View all
Common terms and phrases
activities actual additional Agreement alternative amount applicable approach approval Architect award basic bidders budget building changes Chapter chart compared completion concepts concrete considerations contract contractor cost detailed determine developed direct documents drawings economic effect engineering equipment estimate evaluation example facilities factors field Figure finish firms important individual industry inspection involved knowledge labor major materials methods needed negotiated objectives obtain operations organization overall owner packages payment percent performance period phase planning plant practices preliminary prepared problems procedures procurement productivity professional construction manager progress proposed quantities reasonable reports responsibilities safety savings schedule scope selection separate shows specifications standard Structural subcontractors summary testing tion Trade traditional unassigned unit utilities value engineering warehouse