Professional Construction Management |
From inside the book
Results 1-3 of 88
Page 255
Example Figure 13-3 gives an example of a code for a particular item in a a project cost code . Here the project code 78NB04 means that this is the fourth ( 04 ) negotiated ( N ) building construction ( B ) job started in 1978 ...
Example Figure 13-3 gives an example of a code for a particular item in a a project cost code . Here the project code 78NB04 means that this is the fourth ( 04 ) negotiated ( N ) building construction ( B ) job started in 1978 ...
Page 361
Unit cost Description Quantity Labor Mat'l Building Finish , cont'd . Furnishings & Equipment Adjustable Dock Ramps Permanent Dock Boards Door Seals Jib Crane Double Post Lift Direct Cost 500.00 2200.00 100.00 200.00 300.00 600.00 ...
Unit cost Description Quantity Labor Mat'l Building Finish , cont'd . Furnishings & Equipment Adjustable Dock Ramps Permanent Dock Boards Door Seals Jib Crane Double Post Lift Direct Cost 500.00 2200.00 100.00 200.00 300.00 600.00 ...
Page 440
Building Estimator's Reference Book , 18th ed . , The Frank R. Walker Co. , Chicago , 1973 . Construction Users Anti - Inflation Roundtable , “ Effect of Scheduled Overtime on Construction Projects , ” AACE Bulletin , vol . 15 , no .
Building Estimator's Reference Book , 18th ed . , The Frank R. Walker Co. , Chicago , 1973 . Construction Users Anti - Inflation Roundtable , “ Effect of Scheduled Overtime on Construction Projects , ” AACE Bulletin , vol . 15 , no .
What people are saying - Write a review
We haven't found any reviews in the usual places.
Contents
Constructions Future 3 5 Cz | 6 |
What Is Professional Construction Management? | 13 |
MANAGEMENT IN PRACTICE | 15 |
Copyright | |
20 other sections not shown
Other editions - View all
Common terms and phrases
activities actual additional Agreement alternative amount applicable approach approval Architect award basic bidders budget building changes Chapter chart compared completion concepts concrete considerations contract contractor cost detailed determine developed direct documents drawings economic effect engineering equipment estimate evaluation example facilities factors field Figure finish firms important individual industry inspection involved knowledge labor major materials methods needed negotiated objectives obtain operations organization overall owner packages payment percent performance period phase planning plant practices preliminary prepared problems procedures procurement productivity professional construction manager progress proposed quantities reasonable reports responsibilities safety savings schedule scope selection separate shows specifications standard Structural subcontractors summary testing tion Trade traditional unassigned unit utilities value engineering warehouse