Professional Construction ManagementThe subjects covered in this book include those normally studied in an introductory overview course on construction management, and there is enough depth and added material to serve as the basis for a more advanced course, focusing on organizational and contractual approaches to project management, and the related planning and control systems. This new edition strengthens its coverage of the business aspects of the industry, with a section devoted solely to the business methods in professional construction management. The text's practical in-depth approach to the major engineering and management techniques appeals to both students and practitioners alike. Copyright © Libri GmbH. All rights reserved. |
From inside the book
Results 1-3 of 85
Page 134
Figure 8-3 shows a similar report after nine contracts have been awarded and a fair - cost estimate has been completed for the balance of the work . The evaluated contingency reflects the definitive nature of this state of the project .
Figure 8-3 shows a similar report after nine contracts have been awarded and a fair - cost estimate has been completed for the balance of the work . The evaluated contingency reflects the definitive nature of this state of the project .
Page 227
Basic concepts of planning , reporting , comparing , and projecting progress are shown on Figure 12-7 . Early , Late , and Actual Progress This section requires some understand- ing of the critical path network concepts discussed later ...
Basic concepts of planning , reporting , comparing , and projecting progress are shown on Figure 12-7 . Early , Late , and Actual Progress This section requires some understand- ing of the critical path network concepts discussed later ...
Page 340
DRIVE DRIVE A : disk DRIVE 2 DRIVE B : Figure 17-6 : Drive for " Floppy " Diskettes characters ( Figure 17-7 ) , on up to fixed - pack " winchester " disks with capacities of up to 1 billion characters . The cost of comparable drives ...
DRIVE DRIVE A : disk DRIVE 2 DRIVE B : Figure 17-6 : Drive for " Floppy " Diskettes characters ( Figure 17-7 ) , on up to fixed - pack " winchester " disks with capacities of up to 1 billion characters . The cost of comparable drives ...
What people are saying - Write a review
We haven't found any reviews in the usual places.
Contents
Professional Construction Management in | 3 |
MANAGEMENT IN PRACTICE | 15 |
Development and Organization of Projects | 18 |
Copyright | |
29 other sections not shown
Other editions - View all
Common terms and phrases
acceptance activities actual additional Agreement alternative amount applicable approach approval Architect associated award basic become bidders budget building changes chapter chart claims Company completion concept concrete considerations contract Contractor cost detail determine developed direct documents drawings economic effect engineering equipment estimate evaluation example facilities factors field Figure final finish firms important individual industry inspection involved labor major materials methods needed negotiated objectives operations organization overall Owner packages payment percent performance period phase planning practices preliminary prepared problems procedures procurement productivity professional construction manager progress proposed quantities reasonable reports responsibilities safety savings schedule shown shows Special specifications standard Structural Subcontractor testing tion Trade unassigned union unit warehouse