Deskbook for the Contractor and ManagerPrentice-Hall, 1986 - 264 pages |
From inside the book
Results 1-3 of 15
Page 256
... Bidder has been extended to inc 2. ARTICLE 2 - BIDDER'S REPRESENTATIONS : de those submitting Bids for designated portions of the Work . As stipulated in AIA Document A201 Subparagraph 1.2.2 , the Bidder makes an additional ...
... Bidder has been extended to inc 2. ARTICLE 2 - BIDDER'S REPRESENTATIONS : de those submitting Bids for designated portions of the Work . As stipulated in AIA Document A201 Subparagraph 1.2.2 , the Bidder makes an additional ...
Page 259
Byron W. Maguire. INSTRUCTIONS TO BIDDERS M AIA DOCUMENT A701 INSTRUCTIONS TO BIDDERS THIRD EDITION THE AMERICAN ... Bidder offers to perform the Work described in the Bidding Documents as the base to which work may be added or from ...
Byron W. Maguire. INSTRUCTIONS TO BIDDERS M AIA DOCUMENT A701 INSTRUCTIONS TO BIDDERS THIRD EDITION THE AMERICAN ... Bidder offers to perform the Work described in the Bidding Documents as the base to which work may be added or from ...
Page 261
... Bidder or by telegram ; if by telegram , written confirmation ' over the signature of the Bidder shall be mailed and postmarked on or before the date and time set for receipt of Bids , and it shall be so worded as not to reveal the ...
... Bidder or by telegram ; if by telegram , written confirmation ' over the signature of the Bidder shall be mailed and postmarked on or before the date and time set for receipt of Bids , and it shall be so worded as not to reveal the ...
Contents
MANAGEMENT OF THE COMPANY | 26 |
ACCOUNTING RECORD KEEPING AND FINANCIAL REPORTS | 60 |
PROFIT PLANNING CHECKING AND MANAGING | 104 |
Copyright | |
6 other sections not shown
Common terms and phrases
accounts Accounts Payable AIA DOCUMENT A201 AMERICAN INSTITUTE amount arbitration ARTICLE assets budget cash Certificate Change Order chapter company's Contract Documents contract price Contract Sum contractor contribution margin corporation cost-plus pricing crew damages depreciation direct labor EA EA earnings electrician employees equipment estimated example expenses Figure fixed costs goals income indirect INSTITUTE OF ARCHITECTS Instructions to Bidders ledger liability loss Management by objectives materials ment method net present value operation opportunity cost OSHA overhead costs Owner Owner-Contractor Agreement Paragraph parties payable percent performance Performance Bond period person Postal Service profit ratio revenue safety schedule skills sole proprietorship specific standards Subcontractor Subparagraph Subpart Substantial Completion surety tion Total tractor truck U.S. POSTAL SERVICE variable workers XX XX XX YORK AVENUE