(1) A provision increasing the estimated or ceiling amount referred to in the Limitation of Cost clause of the contract and stating that the clause will thereafter apply in respect to the increase amount; or

(2) A provision stating that the estimated or ceiling amount referred to in the contract is not changed by the modification and that the Limitation of Cost clause will continue to apply with respect to the amount in effect prior to the modification.

(b) A fixed-fee provided in a contract shall not be changed when funding a cost overrun. Changes in fixed-fee will be made only to reflect changes in the scope of work which justify an increase or decrease in fee.

PART 345-GOVERNMENT PROPERTY

Subpart 345.3-Providing Government Property to Contractors

Sec.

345.370 Providing Government property (in

general).

Subpart 345.4-Contractor Use and Rental of Government Property

345.405 Contracts with foreign governments or international organizations. AUTHORITY: 5 U.S.C. 301; 40 U.S.C. 486(c). SOURCE: 49 FR 14030, Apr. 9, 1984, unless otherwise noted.

Subpart 345.3-Providing Govern

ment Property to Contractors 345.370 Providing Government property (in general).

(a) A contractor may be provided Government property or allowed to acquire such property at Government expense upon determination that:

(1) No practicable or economical alternative exists; e.g., acquisition from other sources, utilization of subcontractors, rental of property, or modification of program project requirements, etc.;

(2) The Government receives adequate consideration for providing the property; or

(3) Furnishing Government property is likely to result in substantially

lower cost to the Government for the items produced or services rendered when all costs involved (e.g., transportation, installation, modification, maintenance, etc.) are compared with the cost to the Government of the contractor's use of privately-owned property.

(b) The determination that it is necessary to provide a contractor or subcontractor with property will be made by the contracting officer with the advice of the agency property official.

(c) If the program office is aware, prior to the submission of the request for contract, that it will be necessary to provide prospective contractors with property, a written justification must accompany the request for contract to the contracting activity.

[blocks in formation]

and Rental of Government Property

345.405 Contracts with foreign governments or international organizations.

Upon the request of a foreign government or international organization, or a contractor certifying that it is acting on behalf of a foreign government or international organization, the contracting officer, with advice from the agency property official cognizant of Government property located in the United States, its possessions, or Puerto Rico, may give written approval for its use without charge on contracts or subcontracts thereunder if:

(a) The foreign government or international organization would be authorized to place the contract with the activity concerned under the Foreign Assistance Act of 1961, as amended, or such use is authorized by an agreement with the foreign government;

(b) The foreign government's placement of the contract directly with the contractor is consistent with the best interests of the United States;

(c) It appears that the foreign government will place the contract with the contractor whether or not use is authorized, and no competitive pricing advantage will accrue to the contractor by virtue of its use;

(d) The contractor agrees that no charge for the use of the property will

SUBCHAPTER H-CLAUSES AND FORMS

[blocks in formation]

of the Department of Health and Human Services; and the term "his/her duly authorized representative" means any person, persons, or board authorized to act for the Secretary.

(b) The term Contracting Officer means a person with the authority to enter into, administer, and/or terminate contracts and make related determinations and findings. The term includes certain authorized representatives of the Contracting Officer acting within the limits of their authority as delegated by the Contracting Officer.

(c) The term Project Officer means the person representing the Government for the purpose of technical monitoring of contract performance. The Project Officer is not authorized to issue any instructions or directions which effect any increases or decreases in the scope of work or which would result in the increase or decrease of the price of this contract or a change in the delivery dates or performance period of this contract.

(d) The term Department means the Department of Health and Human Services.

(e) Except as otherwise provided in this contract, the term subcontract includes purchase order under this contract.

(End of clause)

Alternate I (Apr 1984). For cost-reimbursement contracts other than purchase orders, delete paragraph (c) above and replace with the following paragraph (c):

(c) The term Project Officer means the person representing the Government for the purpose of technical monitoring of contract performance. The Project Officer is not authorized to issue any instructions or directions which effect any increases or decreases in the scope of work or which would result in the increase or decrease of the cost of this contract or a change in performance period of this contract. In addition, the Project Officer is not authorized to receive or act upon the Contractor's notification of a revised cost estimate pursuant to the Limitation of Cost or Limitation of Funds clause of this contract.

[49 FR 14031, Apr. 9, 1984, as amended at 53 FR 15564, May 2, 1988]

[blocks in formation]

PART 339-MANAGEMENT, ACQUISITION, AND USE OF INFORMATION RESOURCES

Subpart 339.70-ADP Clearances and Systems Security

Sec.

339.7001 ADP Clearances.

339.7002 ADP systems security.

AUTHORITY: 5 U.S.C. 301; 40 U.S.C. 486 (c). SOURCE: 49 FR 14023, Apr. 9, 1984, unless otherwise noted.

Subpart 339.70-ADP Clearances and Systems Security

339.7001 ADP clearances.

In accordance with Chapter 4-10 of the HHS Information Resources Management (IRM) Manual, the Office of Information Resources Management (OIRM), OASMB-OS, is responsible for the review and approval of all requests for proposed automatic data processing (ADP) systems and modifications to existing ADP systems which require the acquisition of ADP hardware, software packages, and services, and telecommunications equipment, which exceed the dollar thresholds stated in Chapter 4-10.

(a) It is the responsibility of the program office to obtain written approval from OIRM on proposed ADP acquisitions which exceed the thresholds stated in Exhibit 4-10-A of Chapter 4-10 prior to submitting the request for contract to the contracting activity.

(b) The OIRM approval document (delegation of procurement authority (DPA)) is to be attached to the request for contract when it is submitted by the program office to the contracting activity. The contracting activity shall not issue a solicitation based on the request for contract until a properly executed approval document (DPA) is obtained.

[49 FR 14023, Apr. 9, 1984, as amended at 53 FR 43208, Oct. 26, 1988]

339.7002 ADP systems security.

(a) Program responsibilities. Whenever a proposed contract action requires the design, development, maintenance, or use of an ADP system or the use of ADP resources, the program office is

required to designate a responsible individual to serve as the ADP system manager who is to ensure, in coordination with the cognizant systems security officer, that ADP security requirements are met and that each contractor maintains an acceptable security program. The project officer is responsible for setting forth the specific portions of Part 6, ADP Systems Security, of the HHS IRM Manual which are applicable to the instant acquisition.

(b) Contracting responsibilities. (1) The contracting officer is responsible for ensuring that a certification of ADP systems security requirements, signed by both the ADP system manager and the ADP systems security officer, is submitted with the request for contract. The contracting officer shall not initiate action on the request for contract until the properly executed certification is received. The certification I will state that the security requirements specified are reasonably sufficient for the intended application and that they comply with current Federal and HHS computer security policies, procedures, standards, and guidelines.

(2) When developing the request for proposals, the contracting officer shall include in the technical proposal instructions a statement requiring that the offeror present a detailed outline of its proposed ADP system security program which complies with the requirements of the statement of work and applicable portions of Part 6, ADP Systems Security, of the HHS IRM Manual.

(3) The contracting officer shall include a special provision reading substantially as follows in all applicable solicitations and resultant contracts:

The Contractor agrees to comply with the ADP system security requirements set forth in the system of work and applicable portions of Part 6, ADP Systems Security, of the HHS IRM Manual. The Contractor further agrees to include this provision in any subcontract awarded pursuant to this prime contract.

(4) The contracting officer shall ensure that a properly executed certification confirming that the offerors comply with the necessary security requirements is attached to the technical evaluation report received from the evaluation panel before proceeding

with the acquisition process. This certification must be countersigned by the officials designated in paragraph (b)(1)

above and must contain a similar statement of compliance.

[49 FR 14023, Apr. 9, 1984, as amended at 53 FR 43208, Oct. 26, 1988]