"b. The Commission shall follow the provisions of section 9(b) of the Administrative Procedure Act in revoking any license.

80 Stat. 388, 5 U.S.C. 558(b).

"c. Upon revocation of the license, the Commission may immediately retake possession of all special nuclear material held by the licensee. In cases found by the Commission to be of extreme importance to the national defense and security or to the health and safety of the public, the Commission may recapture any special nuclear material held by the licensee or may enter upon and operate the facility prior to any of the procedures 5 U.S.c. 551. provided under the Administrative Procedure Act. Just compensation shall be paid for the use of the facility.

of license.

sec. 2237.

facilities. 12 U.S.C.

sec. 2238.

"SEC. 187. MODIFICATION OF LICENSE.-The terms and Modification conditions of all licenses shall be subject to amendment, 42 U.S.C. revision, or modification, by reason of amendments of this Act, or by reason of rules and regulations issued in accordance with the terms of this Act. "SEC. 188. CONTINUED OPERATION OF FACILITIES.- Continued operation of Whenever the Commission finds that the public convenience and necessity or the production program of the Commission requires continued operation of a production facility or utilization facility the license for which has been revoked pursuant to section 186, the Commission may, after consultation with the appropriate regulatory agency, State or Federal, having jurisdiction, order that possession be taken of and such facility be operated for such period of time as the public convenience and necessity or the production program of the Commission. may, in the judgment of the Commission, require, or until a license for the operation of the facility shall become effective. Just compensation shall be paid for the use of the facility.

"SEC. 189. HEARINGS AND JUDICIAL REVIEW.—

Hearings and
Judicial
review.
sec. 2239.

42 U.S.C.

"a. In any proceeding under this Act, for the granting, suspending, revoking, or amending of any license or construction permit, or application to transfer control, and in any proceeding for the issuance or modification of rules and regulations dealing with the activities of licensees, and in any proceeding for the payment of compensation, an award, or royalties under sections 153, 157, 186 c., or 188, the Commission shall grant a hearing upon the request of any person whose interest may be affected by the proceeding, and shall admit any such person as a party to such proceeding. The Commission shall hold a hearing after thirty days' notice and publication once Publication in the Federal Register, on each application under section 103 or 104 b. for a construction permit for a facility, and on any application under section 104 c. for a construction permit for a testing facility. In cases where such a construction permit has been issued following the holding of such a hearing, the Commission may, in the

in F.R.

[blocks in formation]

5 U.S.C. 701706, 28 U.S.C. 2341-2352.

42 U.S.C. sec. 2240.

Atomic Safety
and Licensing
Board

80 Stat. 386,
387, 5 U.S.C.
556 557.
42 U.S.C.

вес. 2241.

absence of a request therefor by any person whose interest may be affected, issue an operating license or an amendment to a construction permit or an amendment to an operating license without a hearing, but upon thirty days' notice and publication once in the Federal Register of its intent to do so. The Commission may dispense with such thirty days' notice and publication with respect to any application for an amendment to a construction permit or an amendment to an operating license upon a determination by the Commission that the amendment involves no significant hazards consideration.69

"b. Any final order entered in any proceeding of the kind specified in subsection a. above shall be subject to judicial review in the manner prescribed in the Act of December 29, 1950, as amended (ch. 1189, 64 Stat. 1129), and to the provisions of section 10 of the Administrative Procedure Act, as amended.

"SEC. 190. LICENSEE INCIDENT REPORTS.-No report by any licensee of any incident arising out of or in connection with a licensed activity made pursuant to any requirement of the Commission shall be admitted as evidence in any suit or action for damages growing out of any matter mentioned in such report.70

"SEC. 191. ATOMIC SAFETY AND LICENSING BOARD."a. Notwithstanding the provisions of sections 7(a) and 8(a) of the Administrative Procedure Act, the Commission is authorized to establish one or more atomic safety and licensing boards, each comprised of three members, one of whom shall be qualified in the conduct of administrative proceedings and two of whom shall have such technical or other qualifications as the Commission deems appropriate to the issues to be decided, to conduct such hearings as the Commission may direct and make such intermediate or final decisions as the Commission may authorize with respect to the granting, suspending, revoking or amending of any license or authorization under the provisions of this Act, any other provision of law, or any regulation of the Commission issued there

Public Law 87-615 (76 Stat. 409) (1962), sec. 2, amended this section. Before amendment it read: "SEC. 189. HEARINGS AND JUDICIAL REVIEW.

"a. In any proceeding under this Act. for the granting, suspending revoking, or amending of any license or construction permit, or application to transfer control, and in any proceeding for the issuance or modifi cation of rules and regulations dealing with the activities of licensees, and in any proceeding for the payment of compensation, an award or royalties under sections 153, 157, 186 c., or 188, the Commission shall grant a hearing upon the request of any person whose interest may be affected by the proceeding, and shall admit any such person as a party to such proceeding. The Commission shall hold a hearing after thirty days notice and publication once in the Federal Register on each application under section 103 or 104 b. for a license for a facility, and on any application under section 104 c. for a license for a testing facility."

Public Law 85-256 (71 Stat. 576) (1957), sec. 7, had previously amended sec. 189 a. by adding the last sentence thereof.

70 Sec. 190 was added by Public Law 87-206 (75 Stat. 475) (1961), Bec. 16.

under." The Commission may delegate to a board such other regulatory functions as the Commission deems appropriate. The Commission may appoint a panel of qualified persons from which board members may be selected.

"b. Board members may be appointed by the Commission from private life, or designated from the staff of the Commission or other Federal agency. Board members appointed from private life shall receive a per diem compensation for each day spent in meetings or conferences, and all members shall receive their necessary traveling or other expenses while engaged in the work of a board. The provisions of section 163 shall be applicable to board members appointed from private life. 72

"SEC. 192. TEMPORARY OPERATING LICENSE."a. In any proceeding upon an application for an operating license for a nuclear power reactor, in which a hearing is otherwise required pursuant to section 189 a., the applicant may petition the Commission for a temporary operating license authorizing operation of the facility pending final action by the Commission on the application. Such petition may be filed at any time after filing of: (1) the report of the Advisory Committee on Reactor Safeguards required by subsection 182 b.; (2) the safety evaluation of the application by the Commission's regulatory staff; and (3) the regulatory staff's final detailed statement on the environmental impact of the facility prepared pursuant to section 102(2)(C) of the National Environmental Policy Act of 1969 (83 Stat. 853) or, in the case of an application for operating license filed on or before September 9, 1971, if the regulatory staff's final detailed statement required under section 102 (2) (C) is not completed, the Commission must satisfy the applicable requirements of the National Environmental Policy Act prior to issuing any temporary operating license under this section 192. The petition shall be accompanied by an affidavit or affidavits setting forth the facts upon which the petitioner relies to justify issuance of the temporary operating license. Any party to the proceeding may file affidavits in support of, or opposition to, the petition within fourteen days

Public Law 91-560 (84 Stat. 1472) (1970), sec. 10, amended the first sentence of subsec. 191 a. Before amendment it read as follows: "Notwithstanding the provisions of sections 7(a) and 8(a) of the Administrative Procedure Act, the Commission is authorized to establish one or more atomic safety and licensing boards, each composed of three members, two of whom shall be technically qualified and one of whom shall be qualified in the conduct of administrative proceedings, to conduct such hearings as the Commission may direct and make such intermediate or final decisions as the Commission may authorize with respect to the granting, suspending, revoking or amending of any license or authorization under the provisions of this Act. any other provision of law, or any regulation of the Commission issued hereunder."

72 Sec. 191 was added by Public Law 87-615 (76 Stat. 409) (1962), sec. 1.

Temporary licensing

authority. 42 U.S.C.

sec. 2242.

after the filing of such petition, or within such additional time not to exceed ten days as may be fixed by the Commission. The Commission shall hold a hearing after ten days' notice and publication once in the Federal Register on any such petition and supporting material filed under this section and the decision of the Commission with respect to the issuance of a temporary operating license, following such hearing, shall be on the basis of findings on the matters specified in subsection b. of this section. The hearing required by this section and the decision of the Commission on the petition shall be conducted with expedited procedures as the Commission may by rule, regulation, or order deem appropriate for a full disclosure of material facts on all substantial issues raised in connection with the proposed temporary operating license.

"b. With respect to any petition filed pursuant to subsection a. of this section, the Commission shall issue a temporary operating license upon finding that:

"(1) the provisions of section 185 have been met with respect to the temporary operating license;

"(2) operation of the facility during the period of the temporary operating license in accordance with its terms and conditions will provide adequate protection of the environment during the period of the temporary operating license; and

"(3) operation of the facility in accordance with the terms and conditions of the temporary operating license is essential toward insuring that the power generating capacity of a utility system or power pool is at, or is restored to, the levels required to assure the adequacy and reliability of the power supply, taking into consideration factors which include, but need not be limited to, alternative available sources of supply, historical reserve requirements for the systems involved to function reliably, the possible endangerment to the public health and safety in the event of power shortages, and data from appropriate Federal and State governmental bodies which have official responsibility to assure an adequate and reliable power supply.

The temporary license shall contain such terms and conditions as the Commission may deem necessary, including the duration of the license and any provision for the extension thereof, and the requirement that the licensee not retire or dismantle any of its existing generating capacity on the ground of the availability of the capacity from the facility which is operating under the temporary license. Any decision or other document authorizing the issuance of any temporary license pursuant to this section shall recite with specificity the reasons justifying the issuance. The decision of the Commission with respect to the issuance of a temporary operating license shall be

subject to judicial review pursuant to the Act of December 29, 1950, as amended (ch. 1189, 64 Stat. 1129).

"c. The hearing on the application for the final operating license otherwise required pursuant to section 189 a. shall be concluded as promptly as practicable. The Commission shall vacate the temporary operating license if it finds that the applicant is not prosecuting the application for the final operating license with due diligence. Issuance of a temporary operating license pursuant to subsection b. of this section shall be without prejudice to the position of any party to the proceeding in which a hearing is otherwise required pursuant to section 189 a.; and failure to assert any ground for denial or limitation of a temporary operating license shall not bar the assertion of such ground in connection with the issuance of a subsequent final operating license.

"d. The authority under this section shall expire on October 30, 1973.73

"CHAPTER 18. ENFORCEMENT

"SEC. 221. GENERAL PROVISIONS.74 "a. To protect against the unlawful dissemination of Restricted Data and to safeguard facilities, equipment, materials, and other property of the Commission, the President shall have authority to utilize the services of any Government agency to the extent he may deem necessary or desirable.

73 Sec. 192 was added by Public Law 92-307 (86 Stat. 191) (1972). 74 Public Law 95-110 (91 Stat. 884) (1977), sec. 302 (a), repealed chapter 17. Prior to repeal, chapter 17 read as follows:

"CHAPTER 17. JOINT COMMITTEE ON ATOMIC ENERGY

"SEC. 201. MEMBERSHIP.-There is hereby established a Joint Committee on Atomic Energy to be composed of nine Members of the Senate to be appointed by the President of the Senate, and nine Members of the House of Representatives to be appointed by the Speaker of the House of Representatives. In each instance not more than five Members shall be members of the same political party.

"SEC. 202. AUTHORITY AND DUTY.

"a. The Joint Committee shall make continuing studies of the activities of the Atomic Energy Commission and of problems relating to the development, use, and control of atomic energy. During the first ninety days of each session of the Congress, the Joint Committee may conduct hearings in either open or executive session for the purpose of receiving information concerning the development, growth, and state of the atomic energy industry. The Commission shall keep the Joint Committee fully and currently informed with respect to all of the Commission's activities. The Department of Defense shall keep the Joint Committee fully and currently informed with respect to all matters within the Department of Defense relating to the development, utilization, or application of atomic energy. Any Government agency shall furnish any information requested by the Joint Committee with respect to the activities or responsibilities of that agency in the field of atomic energy. All bills, resolutions, and other matters in the Senate or the House of Representatives relating primarily to the Commission or to the development, use, or control of atomic energy shall be referred to the Joint Committee. The members of the Joint Committee who are Members of the Senate shall from time to time report to the Senate, and the members of the Joint Committee who are Members of the House of Representatives shall from time to time report to the House, by bill or otherwise, their recommendations with respect to matters within the jurisdiction of their respective Houses which are referred to the Joint Committee or otherwise within the jurisdiction of the Joint Committee. (Continued)

General provisions.

2 U.S.C. sec. 2271.