Page images
PDF
EPUB

Amount appropriated by act approved September 19, 1890.
June 30, 1891, amount expended during fiscal year

$25,000.00 1,835. 73

July 1, 1891, balance unexpended.

July 1, 1891, outstanding liabilities...

[blocks in formation]

July 1, 1891, amount covered by uncompleted contracts...

[blocks in formation]

July 1, 1891, balance available.....

145,000.00

(Amount (estimated) required for completion of existing project........... Amount that can be profitably expended in fiscal year edning June 30, 1893 100,000.00 Submitted in compliance with requirements of sections 2 of river and harbor acts of 1866 and 1867.

(See Appendix N 3.)

4. Altamaha River, Georgia.-The plan of improvement under which operations have been carried on upon the Altamaha River during the last fiscal year was adopted in 1890.

The project contemplates the establishment of a steamboat channel 3 feet in depth at ordinary summer low water between Darien and the junction of the Oconee and Ocmulgee rivers.

The estimated cost of the improvement is $129,000.

Prior to improvement navigation was much impeded by logs, snags, and other obstructions, the low-water depth at some points not exceeding 2 feet.

During the fiscal year just closed 150 snags, stumps, and logs, and 466 overhanging trees were removed; 4 trees were pulled back, and 2 logs were cut up on bank.

The expenditures during the year amounted to $1,946.79.

The total amount expended under the present project to June 30, 1891, including all outstanding liabilities, is $2,446.79, and has resulted in removing many of the most dangerous snags and overhanging trees.

July 1, 1890, balance unexpended.....

Amount appropriated by act approved September 19, 1890.

[blocks in formation]

(Amount (estimated) required for completion of existing project.. Amount that can be profitably expended in fiscal year ending June 30,1893 Submitted in compliance with requirements of sections 2 of river and harbor acts of 1866 and 1867.

(See Appendix N 4.)

$223.41 15,000.00

15, 223. 41 1,946.79

13, 276.62 500.00

12, 776.62

114,000.00 45,000.00

5. Oconee River, Georgia.-The plan of improvement under which operations have been carried on upon the Oconee River during the last fiscal year was adopted in 1890.

The project contemplates the establishment of a steamboat channel 3 feet in depth at ordinary summer low water between Milledgeville and the mouth of the river.

The estimated cost of the improvement is $171,000.

Prior to improvement navigation was much impeded by sand bars, overhanging trees, snags, and sunken logs. On some shoals there were low-water depths of not more than 2 feet. During the fiscal year just closed 1,135 logs, snags, and stumps, and 146 overhanging trees were removed, 600 cubic yards of stone were placed in a closing dam at

Fish Trap Cut, and 19 piles were driven and 11 brush mats sunk at Old Boat Yard in constructing contracting works at that point.

The expenditures during the year amounted to $8,120.31. The total amount expended under the present project to June 30, 1891, including all outstanding liabilities, is $8,120.31, and has resulted in so improv ing the river that boats now run at a stage of water 4 feet lower than before improvements were begun.

July 1, 1890, balance unexpended ...

Amount appropriated by act approved September 19, 1890

June 30, 1891, amount expended during fiscal year............

201.18 25,000.00

25, 201.18 8, 120.31

[blocks in formation]

146,000.00

Amount (estimated) required for completion of existing project.
Amount that can be profitably expended in fiscal year ending June 30, 1893 50,000.00
Submitted in compliance with requirements of sections 2 of river and

harbor acts of 1866 and 1867.

(See Appendix N 5.)

6. Ocmulgee River, Georgia.-The plan of improvement under which operations have been carried on upon the Ocmulgee River during the last fiscal year was adopted in 1890. The project contemplates the establishment of a steamboat channel 3 feet in depth at ordinary summer low water between Macon and the mouth of the river.

The estimated cost of the improvement is $210,000.

Prior to improvement navigation was much impeded by rock shoals, sand bars, overhanging trees, snags, and sunken logs, the low-water depth at some places not exceeding 2 feet.

During the fiscal year just closed 173 snags and logs, 13 stumps, and 520 overhanging trees were removed, 8 trees were deadened, and 14 logs cut up on the river bank. The expenditures during the year amounted to $12,575.89. The total amount expended to June 30, 1891, including all outstanding liabilities, is $13,099.69, and has resulted in removing many dangerous obstructions, boats now being able to run without accident at a stage of water some 3 feet lower than before the improvements were begun.

July 1, 1890, balance unexpended..........

Amount appropriated by act approved September 19, 1890

$244.95 30,000.00

[blocks in formation]

July 1, 1891, amount covered by uncompleted contracts.............

$523.80

[blocks in formation]

July 1, 1891, balance available..............

11, 205. 26

180,000.00

Amount (estimated) required for completion of existing project.
Amount that can be profitably expended in fiscal year ending June 30, 1893 50,000.00
Submitted in compliance with requirements of sections 2 of river and
harbor acts of 1-66 and 1867.

(See Appendix N 6.)

7. Brunswick Harbor, Georgia.—The plan of improvement under which operations have been carried on in Brunswick Harbor during the last fiscal year was adopted in 1880 and modified and enlarged in 1886.

The project contemplates the establishment of, a navigable channel not less than 15 feet deep at mean low water. The mean rise and fall of tide is 6.8 feet.

The cost of the project of 1880 was estimated at $73,187.50, and as enlarged in 1886 at $190,000, inclusive of appropriations already made. In 1880, prior to improvement, the channel was not more than 9 feet deep at mean low water.

During the fiscal year just closed 7,976.48 cubic yards of brush fas cines and 1,737.93 cubic yards of stone were placed in the training wall. The expenditures during the year amounted to $20,209.88. The amount expended to June 30, 1891, including all outstanding liabilities, is $147,667.61, and has resulted in securing a navigable low-water channel not less than 15 feet deep.

July 1, 1890, balance unexpended..........

Amount appropriated by act approved September 19, 1890..

June 30, 1891, amount expended during fiscal year....

$42.27

35,000.00

35, 042. 27 20, 209.88

July 1, 1891, balance unexpended.....

July 1, 1891, amount covered by uncompleted contracts....

July 1, 1891, balance available......

Amount (estimated) required for completion of existing project..

[blocks in formation]

Amount that can be profitably expended in fiscal year ending June 30, 1893 27,500.00 Submitted in compliance with requirements of sections 2 of river and

harbor acts of 1866 and 1867.

(See Appendix N 7.)

8. Jekyl Creek, Georgia.-The plan of improvement under which operations have been carried on in Jekyl Creek during the last fiscal year was adopted in 1888. The project contemplates the establishment of a navigable channel through the creek 7 feet deep at mean low water. The mean and rise and fall of tide is about 7,1 feet.

The estimated cost of the improvement is $38,590.

Prior to improvement the low-water depth at some places did not exceed 3 feet.

During the fiscal year just closed a foundation course of training wall, 514.5 feet in length and 40 feet in width, was constructed at the mouth of the creek. There were used 2,282.22 square yards of log and brush mattresses, 28.17 cubic yards of brush fascines, and 336.18 cubic yards of stone. The expenditures during the year amounted to $3,919.60. The amount expended to June 30, 1891, including all outstanding liabilities, is $8,888.22, and has resulted in securing a navigable channel with a low-water depth of not less than 5 feet.

July 1, 1890, balance unexpended......

Amount appropriated by act approved September 19, 1890....

June 30, 1891, amount expended during fiscal year

July 1, 1891, balance unexpended ....

July 1, 1891, amount covered by uncompleted contracts....

$31.38 7,500.00

7,533.80

3, 919. 61

3,611.78 3,000.00

611.78

July 1, 1891, balance available

Amount (estimated) required for completion ofexisting project...
Amount that can be profitably expended in fiscal year ending June 30, 1893
Submitted in compliance with requirements of sections 2 of river and
harbor acts of 1866 and 1867.

(See Appendix N 8.)

26,090.00

26,090. 00

9. Cumberland Sound, Georgia and Florida.-The plan of improvement under which operations have been carried on at Cumberland Sound during the last fiscal year was adopted in 1879, and revised in 1891. The project contemplates the establishment of a navigable channel across the bar 19 feet deep at mean low water. The mean rise and fall of tide is 5.9 feet. The estimated cost of the improvement is $2,079,500, exclusive of work done prior to 1891.

Prior to improvement the low-water depth of the entrance varied from 11 to 12.5 feet, with a mean rise and fall of tide of 5.9 feet.

During the fiscal year just closed there were placed in the north jetty 2,769.35 square yards of brush mattresses and 382.38 cubic yards of stone, extending the foundation course 267.4 feet. The expenditures during the year amounted to $1,775.95. The total amount expended to June 30, 1891, including all outstanding liabilities, is $488,347.

July 1, 1890, balance unexpended..........

Amount appropriated by act approved September 19, 1890

$449.72 112,500.00

112,949.72

June 30, 1891, amount expended during fiscal year..

4,775.94

July 1, 1891, balance unexpended

108, 173.78

July 1, 1891, outstanding liabilities..

July 1, 1891, amount covered by uncompleted contracts..

$4,020.78 90,979.22

95,000.00

July 1, 1891, balance available...

13, 173.78

[ Amount (estimated) required for completion of existing project...... 1,967, 000. 00 Amount that can be profitably expended in fiscal year ending June 20, 1893 ...

Submitted in compliance with requirements of sections 2 of river and harbor acts of 1866 and 1867.

(See Appendix N 9.)

1,000,000.00

10. Removing sunken vessels or craft obstructing or endangering navigation. The wrecks of the steamers Habersham and General Lee, together with some other vessels and barges sunk during the revolutionary and civil wars, were, after due advertisement, removed by contract during the year.

(See Appendix N 10.)

EXAMINATIONS AND SURVEYS FOR IMPROVEMENT, TO COMPLY WITH REQUIREMENTS OF RIVER AND HARBOR ACT APPROVED SEPTEMBER 19, 1890.

The required preliminary examination of Yellow River, Georgia, from the railroad bridge near Covington to the Ocmulgee, with a view of obtain ing a steamboat channel of 5 feet deep at mean low water, was made by the local engineer in charge, Captain Carter, and report thereon submitted through Col. Wm. P. Craighill, Corps of Engineers, Division Engineer, Southeast Division. It is the opinion of Captain Carter, and of the Division Engineer, based upon the facts and reasons given, that this locality is not worthy of improvement. This opinion being concurred in by me, no further survey was ordered. (See Appendix N 11.) The required preliminary examinations of the following localities were made by the local engineer in charge, Captain Carter, and reports thereon submitted through Col. Wm. P. Craighill, Corps of Engineers, Division Engineer, Southeast Division. It is the opinion of Captain Carter, and of the Division Engineer, based upon the facts and reasons

given, that these localities are worthy of improvement. The conclusions of these officers being concurred in by me, Captain Carter was charged with their survey, the reports on which will be submitted when received. 1. The inside route between Savannah, Georgia, and Fernandina, Florida, with a view of obtaining a steamboat channel of 7 feet depth at mean low water.

2. The inside route between Doboy and Sopelo [Sapelo], Georgia, with a view of making the same navigable for sea-going vessels.

3. Brunswick Outer Bar, Georgia, to determine the feasibility and cost of deepening the same to 26 feet at ordinary high water.

IMPROVEMENT OF CERTAIN RIVERS AND HARBORS IN FLORIDA.

Officer in charge, Capt. W. M. Black, Corps of Engineers, with Lieut. D. DuB. Gaillard, Corps of Engineers, under his immediate orders; Division Engineer, Col. Wm. P. Craighill, Corps of Engineers.

1. St. John's River, Florida.-Operations for the improvement of this river have been carried on in conformity with a project submitted in 1879 by the late General Gilmore, Colonel, Corps of Engineers. The plan contemplates the formation of a continuous channel 15 feet deep at mean low water from Jacksonville to the ocean. The points where work is required are in a reach near Dame Point, 12 miles from the mouth, and on the bar at the mouth. Near Dame Point the mean lowwater depth varies from 12 to 13 feet, with a tidal range of 1 to 2 feet. The bar at the mouth is formed of sand. Before work began the mean low-water channel depth across it varied from 5 to 7 feet, with a tidal range of 5.8 feet. The channel across the bar shifted continuously north and south through a mile range. The work was divided into two parts: (1) The formation of a channel across the bar at the mouth, by the concentration and direction of the tidal currents by two jetties, to start from the opposite shores of the entrance, and to converge, until, on the bar, their outer ends should be approximately parallel and 1,600 feet apart; and (2) the improvement of the Dame Point Reach, by dredging, and the construction of works of protection, under a project approved June 11, 1891.

As the improvement at the mouth was at first most urgently needed, the five appropriations up to that of 1886, inclusive, aggregating $675,000, were made for improving "the channel over the bar at the mouth," under the estimate for that part of the total project. Since 1887 the depth on the bar has been greater than that in the Dame Point Reach, and the interests of commerce have demanded that work at the latter point should be started. Accordingly, the appropriations since 1888 were made for improving the river "from Jacksonville to the ocean, including the channel over the bar at the mouth," under the estimate for the entire project.

At the close of the fiscal year 1889-'90, $828,065.21 had been expended. The south jetty had a total length of 7,147 feet. Of this 1,740 were at the full height and capped; 2,740 were built to the height of mean low water, but with insufficient width of crest; for 800 feet further the average low-water depth on the crest was 1 foot; for the remaining distance the jetty crest was about 5 feet below mean low water. The total length of the north jetty was 9,048 feet. Of this 553 feet were built to full height and capped; 6,404 feet were built up to mean low water, with insufficient width of crest; the mean low-water depth over the remaining length averaged 1 to 5 feet. Prior to 1886 the jetties were built of alternate layers of mattresses and rock. Since

« PreviousContinue »