| United States. Court of Claims, Audrey Bernhardt - 1962 - 784 pages
...therewith; (ii) method of shipment or packing; and (iii) place of delivery. If any such change causes an increase or decrease in the cost of, or the time required for, performance of this contract, an equitable adjustment shall be made in the contract price or delivery schedule, or... | |
| 1969 - 256 pages
...meaning of this clause. (c) Determination of contract adjustment. Upon receipt of notice of a changed condition from the contractor, the contracting officer...cost of, or the time required for, performance of the contract, he shall determine and make an equitable adjustment as provided in § 4-4.5317(b). No... | |
| 1964 - 676 pages
...encountered and generally recognized as inhering in work of the character provided for in this contract. The Contracting Officer shall promptly investigate...cost of, or the time required for, performance of this contract, an equitable adjustment shall be made and the contract modified in writing accordingly.... | |
| 1964 - 1202 pages
...encountered and Cencnliy recognized as inhering in work of the character provided for in this contract. The Contracting Officer shall promptly investigate...materially differ and cause an increase or decrease in the Contractor's cost of, or the time required for, performance of this contract, an equitable adjustment... | |
| 1965
...meaning of this clause. (c) Determination of contract adjustment. Upon receipt of notice of a changed condition from the contractor, the contracting officer...if he finds that such conditions do so materially § 4-4.5315 Title 41— Chapter 4 differ and cause an increase or decrease in the cost of, or the time... | |
| 1997 - 640 pages
...specifications. (2) Method of shipment or packing. (3) Place of delivery. (b) If any such change causes an Increase or decrease In the cost of, or the time...required for, performance of any part of the work under this contract, whether or not changed by the order, the Contracting Officer shall make an equitable... | |
| 1998 - 732 pages
...day, days of the week, etc.). (3) Place of performance of the services. (b) If any such change causes an increase or decrease in the cost of, or the time...required for, performance of any part of the work under this contract, or the Contractor's liability under this contract, whether or not changed by the order,... | |
| 1994 - 674 pages
...(2) Method of shipment or packing. (3) Place of delivery. (b) If any such change causes an increasf or decrease in the cost of, or the time required for, performance of any part of the work under this contract, whether or not changed by the order, the Contracting Officer shall make an equitable... | |
| 1971 - 664 pages
...encountered and generally recognized as inhering in work of the character provided for in this contract. The Contracting Officer shall promptly investigate...conditions, and if he finds that such conditions do materially so differ and cause an increase or decrease in the Contractor's cost of, or the time required... | |
| 1982 - 690 pages
...encountered and generally recognized as inhering in work of the character provided for in this contract. The Contracting Officer shall promptly investigate...conditions, and if he finds that such conditions do materially so differ and cause an increase or decrease in the Contractor's cost of, or the time required... | |
| |