... vendors ? How long does it ordinarily take to secure this material ? What is our delivery experience with the customary vendors on this material ? What delivery promises do they make ? If the material is required in a hurry , what vendor ...
... vendors ? How long does it ordinarily take to secure this material ? What is our delivery experience with the customary vendors on this material ? What delivery promises do they make ? If the material is required in a hurry , what vendor ...
Page 60
... vendor suitable ? 31. Can more advantageous purchase be made if requirements are predicted further in advance in ... vendor on this material ? 34. What delivery promises do they make ? 35. Who is the best vendor for this material when it ...
... vendor suitable ? 31. Can more advantageous purchase be made if requirements are predicted further in advance in ... vendor on this material ? 34. What delivery promises do they make ? 35. Who is the best vendor for this material when it ...
Page 89
... vendor who has given the best service in the past can be selected . It is quite possible that , in many cases , the ... Vendor Be Cautioned on Over- shipment ? Some vendors are habitual over- shippers , that is , those who ship more than ...
... vendor who has given the best service in the past can be selected . It is quite possible that , in many cases , the ... Vendor Be Cautioned on Over- shipment ? Some vendors are habitual over- shippers , that is , those who ship more than ...
Contents
Construction Scheduling | 1 |
Purchasing | 119 |
Materials Expediting and Transportation | 145 |
Copyright | |
8 other sections not shown
Common terms and phrases
agreement apply approval arbitration Architect ARTICLE Associated General Contractors bar chart bill of lading bill of material bolt building cable carrier charges chart completion concrete conehead consignee construction contract contractor copy cost covered damage Deatherage delivery demurrage drawings and specifications employee employment engineering equipment erection estimate foreman freight furnish handling inspection issued labor liability load manager ment method necessary operation organization owner party payment performed person pipe pipe Wrenches plans procedure Punches purchase order purchasing agent rates Reamers received record rental requisition rope safety safety engineer scaffolds schedule secured sheet shipment shipper standard steel erector structural steel subcontractor superintendent supply taper shank Drill temporary terials thereof tion Toledo tractor trucks unloading VALVE vendor wages wire Wrenches