Construction Scheduling and ControlMcGraw-Hill, 1965 - 316 pages |
From inside the book
Results 1-3 of 41
Page 101
... signed , including all the general conditions of the con- tract . These are , in most cases , the top sheets of the specifications . Contract Plans . Two complete sets of con- tract drawings , as noted on page of the contract , are to ...
... signed , including all the general conditions of the con- tract . These are , in most cases , the top sheets of the specifications . Contract Plans . Two complete sets of con- tract drawings , as noted on page of the contract , are to ...
Page 128
... signed by the individual or by a member of the firm or an officer of the corporation , with the statement included ... signed , the subcontrac- tor shall sign with the contractor each sheet of the complete sets of drawings and specifica ...
... signed by the individual or by a member of the firm or an officer of the corporation , with the statement included ... signed , the subcontrac- tor shall sign with the contractor each sheet of the complete sets of drawings and specifica ...
Page 205
... SIGNED . DATE 19 . EQUIP . NO .. WANTED . PAINT CHARGE CODE NO . FIG . 4.13 . Construction shop order . DAILY GAS AND OIL DISPENSER'S REPORT Geo . E. Deatherage & Son DATE . SHIFT . EQUIP NO . FUEL KERO- MOTOR OIL GAS DIESEL OIL TRANS ...
... SIGNED . DATE 19 . EQUIP . NO .. WANTED . PAINT CHARGE CODE NO . FIG . 4.13 . Construction shop order . DAILY GAS AND OIL DISPENSER'S REPORT Geo . E. Deatherage & Son DATE . SHIFT . EQUIP NO . FUEL KERO- MOTOR OIL GAS DIESEL OIL TRANS ...
Contents
Construction Scheduling | 1 |
Purchasing | 119 |
Materials Expediting and Transportation | 145 |
Copyright | |
8 other sections not shown
Common terms and phrases
agreement apply approval arbitration Architect ARTICLE Associated General Contractors bar chart bill of lading bill of material bolt building cable carrier charges chart completion concrete conehead consignee construction contract contractor copy cost covered damage Deatherage delivery demurrage drawings and specifications employee employment engineering equipment erection estimate foreman freight furnish handling inspection issued labor liability load manager ment method necessary operation organization owner party payment performed person pipe pipe Wrenches plans procedure Punches purchase order purchasing agent rates Reamers received record rental requisition rope safety safety engineer scaffolds schedule secured sheet shipment shipper standard steel erector structural steel subcontractor superintendent supply taper shank Drill temporary terials thereof tion Toledo tractor trucks unloading VALVE vendor wages wire Wrenches