Page 294
... procedure Job data sheets in job control Job data sheets , standard practice procedure Job overhead accounts Keeping labor costs in field Labor costs to balance payroll Labor distribution , payrolls Labor distribution , small jobs ...
... procedure Job data sheets in job control Job data sheets , standard practice procedure Job overhead accounts Keeping labor costs in field Labor costs to balance payroll Labor distribution , payrolls Labor distribution , small jobs ...
Page 303
... procedure . For this reason a " Suggested Guide for Bidding Procedure on Engineering Construction " was developed by the Joint Cooperative Commit- tee , American Society of Civil Engineers and the Associated General Contractors of Amer ...
... procedure . For this reason a " Suggested Guide for Bidding Procedure on Engineering Construction " was developed by the Joint Cooperative Commit- tee , American Society of Civil Engineers and the Associated General Contractors of Amer ...
Page
... procedure , general , 2-3 Selection of equipment , 198 Sequence activities , 47-48 Sheaves , safety for , 239 ... procedure , job control reports , 285- 288 Standard practice procedure subcontracts , 100-107 Standard procedure for ...
... procedure , general , 2-3 Selection of equipment , 198 Sequence activities , 47-48 Sheaves , safety for , 239 ... procedure , job control reports , 285- 288 Standard practice procedure subcontracts , 100-107 Standard procedure for ...
Contents
Construction Scheduling | 1 |
Purchasing | 119 |
Materials Expediting and Transportation | 145 |
Copyright | |
8 other sections not shown
Common terms and phrases
agreement apply approval arbitration Architect ARTICLE Associated General Contractors bar chart bill of lading bill of material bolt building cable carrier charges chart completion concrete conehead consignee construction contract contractor copy cost covered damage Deatherage delivery demurrage drawings and specifications employee employment engineering equipment erection estimate foreman freight furnish handling inspection issued labor liability load manager ment method necessary operation organization owner party payment performed person pipe pipe Wrenches plans procedure Punches purchase order purchasing agent rates Reamers received record rental requisition rope safety safety engineer scaffolds schedule secured sheet shipment shipper standard steel erector structural steel subcontractor superintendent supply taper shank Drill temporary terials thereof tion Toledo tractor trucks unloading VALVE vendor wages wire Wrenches