Construction Scheduling and ControlMcGraw-Hill, 1965 - 316 pages |
From inside the book
Results 1-3 of 67
Page 132
... less than 90 per cent of the full insurable value thereof , against fire , tornado , windstorm , and water from any sprinkler system . This insurance shall be ob- tained and paid for by the subcontractor , who shall assume all risk of ...
... less than 90 per cent of the full insurable value thereof , against fire , tornado , windstorm , and water from any sprinkler system . This insurance shall be ob- tained and paid for by the subcontractor , who shall assume all risk of ...
Page 231
... less than 6 ft above ground level , or any permanent floor level which projects at least 3 ft beyond the scaffold , except painters ' swinging scaffolds , shall be provided with guardrails not less than 36 in . high and solid toeboards ...
... less than 6 ft above ground level , or any permanent floor level which projects at least 3 ft beyond the scaffold , except painters ' swinging scaffolds , shall be provided with guardrails not less than 36 in . high and solid toeboards ...
Page 240
... less than 4 ft long should be well nailed on two adjacent sides of uprights at the joints . Joints should be stag- gered every other upright . Ledgers should not be less than 2 × 6 , well nailed to the uprights , preferably on the in ...
... less than 4 ft long should be well nailed on two adjacent sides of uprights at the joints . Joints should be stag- gered every other upright . Ledgers should not be less than 2 × 6 , well nailed to the uprights , preferably on the in ...
Contents
Construction Scheduling | 1 |
Purchasing | 119 |
Materials Expediting and Transportation | 145 |
Copyright | |
8 other sections not shown
Common terms and phrases
agreement apply approval arbitration Architect ARTICLE Associated General Contractors bar chart bill of lading bill of material bolt building cable carrier charges chart completion concrete conehead consignee construction contract contractor copy cost covered damage Deatherage delivery demurrage drawings and specifications employee employment engineering equipment erection estimate foreman freight furnish handling inspection issued labor liability load manager ment method necessary operation organization owner party payment performed person pipe pipe Wrenches plans procedure Punches purchase order purchasing agent rates Reamers received record rental requisition rope safety safety engineer scaffolds schedule secured sheet shipment shipper standard steel erector structural steel subcontractor superintendent supply taper shank Drill temporary terials thereof tion Toledo tractor trucks unloading VALVE vendor wages wire Wrenches