Page images
PDF
EPUB

NON-FEDERAL COST:

In accordance with the cost-sharing and financing concepts reflected in the initial authorization and subsequent authorized modifications of the Tensas Basin project including the Water Resources Development Act of 1986, the non-Federal sponsor must comply with the requirements listed below:

[blocks in formation]

Provide lands, easements, rights-of-way, and dredged material disposal areas.

Pay one-half of the separable costs allocated to recreation (except recreational navigation) and bear all costs of operation, maintenance, and replacement of recreation facilities.

Subtotal Non-Federal Costs

[blocks in formation]

Local interests estimate that they have expended at least $5,900,000 in the Tensas Basin on the construction of drainage improvements prior to initiation of the Federal project. They estimate they will spend an additional $47,012,000 in construction on connecting ditches, main laterals, and on-farm drainage improvements. This work is being accomplished as the major outlets are opened. Local drainage and levee districts have reported that they expended approximately $5,388,032 on construction and maintenance of drainage improvements between 1950 and 1985.

[blocks in formation]
[blocks in formation]

Provide lands, easements, rights-of-way, and dredged material disposal areas.

$ 8,402,000

Modify or relocate buildings, utilities, roads, bridges (except railroad bridges), and other facilities, where necessary in the construction of the project.

10,971,000

Pay 5 percent of the costs allocated to flood control to bring the total non-Federal share of flood control costs to 25 percent, and bear all costs of operation, maintenance, and replacement of flood control facilities.

[blocks in formation]

Provide lands, easements, rights-of-way, and dredged material disposal areas.

Pay 5 percent of the costs allocated to flood control to bring the total non-Federal share of flood control costs to 25 percent, and bear all costs of operation, maintenance, and replacement of flood control facilities.

[blocks in formation]
[blocks in formation]

Vicksburg District

112,000

$1,889,000

Tensas Basin, AR and LA

29 JAN 1992

178

[blocks in formation]

Formal assurances have been furnished by eight levee and drainage districts to operate and maintain all units of the project except the Kirsch Lake Canal. Assurances for Lake Chicot Pumping Plant required by PL 91-611 and PL 91-646 were accepted 16 April 1976 and a cost sharing agreement with the Chicot County Rural Development Authority was executed 28 May 1976. All lands for Lake Chicot recreation development were furnished by 30 March 1976.

The local development authority, which provided assurances that it would operate and maintain Corps constructed recreation facilities in the Tensas Basin at Lake Chicot, AR, has since notified the Vicksburg District that it is unable to comply with the assurances previously furnished regarding operation and maintenance of two remaining recreation facilities, and that the two remaining facilities are not needed. The local authority has been informed that based on the fact that the two remaining facilities are not needed, all programmed construction is considered complete and payback of their cost share for construction should begin in accordance with executed assurances. No response has been received from the local development authority.

Red River Backwater Area

Formal assurances were received 12 February 1947 and accepted 24 April 1947 for all project features except the Sicily
Island Area. Assurances of local cooperation were received on 10 February 1981 and accepted 1 April 1981 for the Sicily
Island Area project. The adoption of a constitutional amendment in the general election of 1 February 1972 gave the State
of Louisiana and its agencies authority to comply with the Uniform Relocations Assistance and Real Property Acquisition
Policies Act of 1970 (PL 91-646). Supplemental assurances covering the requirements of PL 91-646 for the Larto Lake to
Jonesville Area were received 9 May 1972 and accepted 25 May 1972. Supplemental assurances covering the requirements of
PL 91-646 for the Tensas-Cocodrie Levee Enlargement were received 1 February 1974 and accepted 7 February 1974.
Supplemental assurances covering the requirements of PL 91-646 for the Tensas-Cocodrie Pumping Plant were received 18 August
1975 and accepted 27 August 1975.

Tensas River and Below Red River Areas

Local cooperation agreements for the Tensas River and Below Red River separable elements will be obtained consistent with the cost sharing and financing concepts reflected in the Water Resources Development Act of 1986. The local sponsor for the Tensas River and the Below Red River elements is the Fifth Louisiana Levee District. A draft Local

[blocks in formation]
[graphic]
[graphic]

Cooperation Agreement was sent to the local sponsor 2 May 1988 for review. The local sponsor indicated in October 1988 that they are unable to cost share these elements in accordance with the Water Resources Development Act of 1986. By resolution dated 15 November 1989, the Levee District has requested the East Carroll and Madison Parish Police Juries to cosponsor this project. However, no formal agreement was received from either police jury.

COMPARISON OF FEDERAL COST ESTIMATES: The current cost estimate of $534,000,000 is an increase of $16,000,000 from the latest estimate ($518,000,000) presented to Congress (FY 1992). This change includes the following items:

[blocks in formation]

STATUS OF ENVIRONMENTAL IMPACT STATEMENT: The final Environmental Impact Statement was filed with the Environmental Protection Agency on Tensas River, LA, on 18 May 1984; Lake Chicot Pumping Plant on 29 August 1975; and the Red River Backwater Area, Sicily Island Area, on 21 May 1982; Below Red River Area on 30 October 1981; Tensas-Cocodrie Pumping Plant on 24 September 1976; and Tensas-Cocodrie Levee Item on 24 September 1976.

OTHER INFORMATION: Funds to initiate construction were appropriated in FY 1947 on Red River Backwater Area and in FY 1948 on Boeuf and Tensas River, Etc.

[blocks in formation]

APPROPRIATION TITLE: Flood Control, Mississippi River and Tributaries, AR, IL, KY, LA, MS, MO, and TN PROJECT: Yazoo Basin, Mississippi (Continuing)

Construction

LOCATION: The project is located in Mississippi and extends generally from Memphis, Tennessee, southward to Vicksburg,
Mississippi, and from the escarpment at Greenwood, westward to the Mississippi River.

DESCRIPTION: The project provides for protection against headwater floods of streams in the basin; against backwater floods
of the Mississippi; and for major drainage in the delta area. The Yazoo Basin can be readily divided into three major flood
control components (the Yazoo Headwater, the Yazoo Backwater, and the Big Sunflower River, Etc., Including Steele Bayou),
the Streambank Erosion Control Evaluation and Demonstration Program, which has been completed, and the Demonstration Erosion
Control Program. All of the work in the project is programmed except for remaining recreation facilities at Grenada Lake
pending development of cost sharing agreements with local interests for construction and non-Federal operation and
maintenance consistent with projects for which recreation facilities are being constructed under the provisions of the
Federal Water Project Recreation Act of 1965 (Public Law 89-72), as amended; remaining work on Rocky Bayou pending a
decision to continue construction in accordance with the cost sharing and financing concepts reflected in the Water
Resources Development Act of 1986; and remaining work on the Yazoo Backwater Pumping Plant pending development of cost
sharing agreements with local interests for construction and non-Federal operation and maintenance in accordance with the
cost sharing and financing concepts reflected in the Water Resources Development Act of 1986.

AUTHORIZATION: Flood Control Acts of 1936, 1937, 1938, 1941, 1944, 1946, 1950, 1962, 1965, and the Water Resources
Development Acts of 1974 and 1986.

REMAINING BENEFIT-REMAINING COST RATIO: 3.9 to 1 at 2-1/2 percent.

TOTAL BENEFIT-COST RATIO: 4.3 to 1 at 2-1/2 percent.

INITIAL BENEFIT-COST RATIO:

2.1 to 1 at 2-1/2 percent (FY 1967).

BASIS OF BENEFIT-COST RATIO:

Benefits and costs for the Yazoo Backwater Pumping Plant are from the latest evaluation
approved in July 1983 at 1980 price levels. Benefits and costs for the remaining features of the Yazoo Basin project are
from the 1974 Mississippi River and Tributaries Update approved in September 1974 at 1974 price levels.

[blocks in formation]
[graphic]
[graphic]
« PreviousContinue »