Handbook of Construction Management and OrganizationVan Nostrand Reinhold, 1973 - 660 pages USA. Manual of and guide to business organization and management techniques for the construction industry - provides advice on the basics of contracting, bidding, financial management, equipment maintenance, network analysis, cost accounting, computerization, labour relations, occupational safety, public relations, taxation, etc. Flow charts, graphs, photographs, references and statistical tables. |
From inside the book
Results 1-3 of 90
Page 159
... possible to locate a wearing part , to monitor its gradual wear , and to correct or replace it before major trouble ... possible to track down trouble . With oil analysis , a slightly cracked block or head , a faulty air cleaner , or a ...
... possible to locate a wearing part , to monitor its gradual wear , and to correct or replace it before major trouble ... possible to track down trouble . With oil analysis , a slightly cracked block or head , a faulty air cleaner , or a ...
Page 434
... possible . Probably the most important of those omitted from the above discussion are ones involving cost control . There are many ways in which costs can be associated with the work breakdown structure and that budgeted costs and ...
... possible . Probably the most important of those omitted from the above discussion are ones involving cost control . There are many ways in which costs can be associated with the work breakdown structure and that budgeted costs and ...
Page 523
... possible , on a line item ( or bid item ) basis . The identification and designation of the line items would be furnished by the original estimate . In other words , it is necessary to correlate the accumulation of cost data on ...
... possible , on a line item ( or bid item ) basis . The identification and designation of the line items would be furnished by the original estimate . In other words , it is necessary to correlate the accumulation of cost data on ...
Other editions - View all
Common terms and phrases
accounting activities actual costs additional agreement AMOUNT UNIT COST application bank basic basis benefits bond BROWN'S FERRY changes charges cofferdam complete concrete contract contractor COST AMOUNT UNIT determined developed diagram Diffusion chamber DIRECT COST DOE CONSTRUCTION COMPANY employees equipment excavation expense facilities factor FICTITIOUS FOR ILLUSTRATION field Figure functions historical cost home office income industry involved job cost JOHN DOE CONSTRUCTION joint venture labor loan loss machine maintenance materials ment method Morrison-Knudsen necessary overhead owner payment payroll percent performance period personnel preventive maintenance procedures profit project engineer project manager punched cards purchase quantities rates records rental repair reports result Riprap schedule subcontractors subnetwork surety surety bond Target Estimate tion tractor UNIT AMOUNT COST UNIT COST AMOUNT usually wage