Handbook of Construction Management and OrganizationVan Nostrand Reinhold, 1973 - 660 pages USA. Manual of and guide to business organization and management techniques for the construction industry - provides advice on the basics of contracting, bidding, financial management, equipment maintenance, network analysis, cost accounting, computerization, labour relations, occupational safety, public relations, taxation, etc. Flow charts, graphs, photographs, references and statistical tables. |
From inside the book
Results 1-3 of 73
Page 80
... bond , however , is a three - party instrument - the principal , who in a contract bond is the contractor ; the obligee or owner , who is a party requiring the protection of the bond ; and the surety . The surety guarantees that the ...
... bond , however , is a three - party instrument - the principal , who in a contract bond is the contractor ; the obligee or owner , who is a party requiring the protection of the bond ; and the surety . The surety guarantees that the ...
Page 83
... Bond Forms A contract bond generally is in the form of a joint and several guarantee of principal and surety to pay a specified sum of money , known as the bond penalty ; subject to ... Bonds 83 Importance of Bank Credit 56 Surety Bond Forms.
... Bond Forms A contract bond generally is in the form of a joint and several guarantee of principal and surety to pay a specified sum of money , known as the bond penalty ; subject to ... Bonds 83 Importance of Bank Credit 56 Surety Bond Forms.
Page 94
... bond , the sureties are jointly and severally liable for the full bond penalty , limited only to the stated dollar amount for which each company signed . 8-15 . Selection of a Bonding Company The proper selection of a bonding company is ...
... bond , the sureties are jointly and severally liable for the full bond penalty , limited only to the stated dollar amount for which each company signed . 8-15 . Selection of a Bonding Company The proper selection of a bonding company is ...
Other editions - View all
Common terms and phrases
accounting activities actual costs additional agreement AMOUNT UNIT COST application bank basic basis benefits bond BROWN'S FERRY changes charges cofferdam complete concrete contract contractor COST AMOUNT UNIT determined developed diagram Diffusion chamber DIRECT COST DOE CONSTRUCTION COMPANY employees equipment excavation expense facilities factor FICTITIOUS FOR ILLUSTRATION field Figure functions historical cost home office income industry involved job cost JOHN DOE CONSTRUCTION joint venture labor loan loss machine maintenance materials ment method Morrison-Knudsen necessary overhead owner payment payroll percent performance period personnel preventive maintenance procedures profit project engineer project manager punched cards purchase quantities rates records rental repair reports result Riprap schedule subcontractors subnetwork surety surety bond Target Estimate tion tractor UNIT AMOUNT COST UNIT COST AMOUNT usually wage