Page images
PDF
EPUB

Amount available July 1, 1871......

Amount required for fiscal year ending June 30, 1873..

See Appendix A 3.)

$14,059 96

25, 000 00

4. Eagle Harbor, Lake Superior, Michigan.-No work has been done at this harbor during the year. A contract was made in December, 1870, to remove a portion of the rock now obstructing the entrance to the harbor; work to commence on the 1st of May, 1871. The contractor has failed to carry out his contract, and the work has been suspended. It has been deemed advisable to await the results of the operations for removing rock obstructions in Hell Gate, East River, New York, before deciding upon a plan for prosecuting this work.

Amount on hand July 1, 1870......

Amount expended during the fiscal year ending June 30, 1871....

Amount available July 1, 1871.........

See Appendix A 4.)

$23, 706 97

150 40

23,556 57

5. Marquette Harbor, Lake Superior, Michigan.-During the year there has been added to the breakwater 200 feet, built to water-surface, and 2 of the 300 feet reported in the last annual report as without superstracture has been completed. It is proposed during the ensuing sea

to have the superstructure of the remaining 100 feet completed, and to extend the breakwater 650 feet sub and superstructure, giving, by June 30, 1873, a complete breakwater 1,850 feet in length, extending to feet of water. The effect of this structure on the harbor is now marked, and the beneficial influence of each addition is experienced at ouce. The original estimate for this breakwater was $385,129 58, and the length designed, 2,050 feet; $190,000 has been appropriated, which will complete 1,850 feet, leaving only 200 feet to complete the work as intended. Owing to the increasing importance of Marquette Harbor and the necessity of its better protection, it is recommended that the work be continued to the amount of the original estimate.

Amount on hand July 1, 1870....

Amount appropriated by act of July 11, 1870..
Amount appropriated by act of March 3, 1871.

Amount expended during the fiscal year ending June 30,
1871.....

Amount available July 1, 1871..

$29, 477 60 25,000 00 60, 000 00

29,459 63 85, 017 91

Amount required for fiscal year ending June 30, 1873..... 100, 000 00

See Appendix A 5.)

6. Menomonee Harbor, Michigan.-An appropriation for the improvesent of this harbor was made by the act of March 3, 1871, and an examination of the locality at once undertaken to ascertain what changes, if any, had taken place since the summer of 1867. A project for improvement, consisting of a pile pier extending in a northeasterly direction to a depth of 15 feet water, in Green Bay, commencing at a pot south of the center of the sand-point forming the north shore of the mouth of the river; this pier to constitute the permanent work of the improvement for the harbor, and to be extended inward, or conected with the south bank of the river, as experience or the rights of [roperty-owners may hereafter determine.

A contract was entered into in June for the construction of the pier, and it is expected that at least 1,000 feet of it will be completed by the close of the present working season.

Amount appropriated by act of March 3, 1871.

Amount expended during the fiscal year ending Jupe 30,

1871 .....

Amount available July 1, 1871..........

Amount required for fiscal year ending June 30, 1873....

(See Appendix A 6.)

$25,000 00

227 50 24, 772 50 25,000 00

7. Green Bay Harbor, Wisconsin.-The work at this harbor during the year has consisted in continuing the dredging south of Grassy Island so as to give a width of 200 feet, and straightening and deepening the area heretofore dredged; in revetting the channel through Grassy Island on the west side; cutting a channel 2,000 feet in length north of that island; extending the revetment on the east side 85 feet, and rip-rapping 450 feet on the east and 280 feet on the west side of the island, to a height of 18 inches above the water surface. It is proposed to dredge a channel 200 feet wide and 14 feet deep south of Grassy Island as far as the mouth of Fox River, and to widen the cut already made on the west side of the island.

The plan of improvement adopted has proved successful, and has secured a safe and commodious harbor at this point, which is of great benefit to the general commerce of the lakes. An examination of

the work shows very little change in the dredged channel.

Amount on hand July 1, 1870...

Amount appropriated by act of July 11, 1870
Amount appropriated by act of March 3, 1871.

Amount expended during the fiscal year ending June 30,
1871....

Amount available July 1, 1871.

Which will complete the work of improvement.

(See Appendix A 7.)

$12, 420 68

17,500 00

17,500 00

28, 103 89 19, 316 79

8. Ahnepee Harbor, Lake Michigan, Wisconsin.-A survey of this harbor was made during the season of 1870, in pursuance of the second section of the act of July 11, 1870, and a plan for its improvement, with estimate of cost, submitted to Congress in January last. An appropriation was made for the improvement by the act of March 3, 1871, and the work contracted for as soon as the necessary arrangements could be perfected. Work under the contract is now progressing favorably. The officer in charge is of the opinion that 600 feet of pier will be completed by the close of the present working season. Amount appropriated by act of March 3, 1871... Amount expended during the fiscal year ending June 30,

1871....

Amount available July 1, 1871 ....

Amount required for fiscal year ending June 30, 1873

(See Appendixes A 8 and A 23.)

$25,000 00

169 40

24,830 60 50, 000 00

9. Two Rivers, Wisconsin.-A survey was made of this locality, as directed by the second section of the act of July 11, 1870, and a plan for its improvement, with estimate of cost, was submitted to Congress in January last. By the act of March 3, 1871, the improvement was

Amount available July 1, 1871..............

Amount required for fiscal year ending June 30, 1873...

(See Appendix A 3.)

$14,059 96 25,000 00

4. Eagle Harbor, Lake Superior, Michigan.-No work has been done at this harbor during the year. A contract was made in December, 1870, to remove a portion of the rock now obstructing the entrance to the harbor; work to commence on the 1st of May, 1871. The contractor has failed to carry out his contract, and the work has been suspended. It has been deemed advisable to await the results of the operations for removing rock obstructions in Hell Gate, East River, New York, before deciding upon a plan for prosecuting this work.

Amount on hand July 1, 1870.....

Amount expended during the fiscal year ending June 30, 1871....

Amount available July 1, 1871....

(See Appendix A 4.)

$23, 706 97

150 40

23, 556 57

5. Marquette Harbor, Lake Superior, Michigan.—During the year there has been added to the breakwater 200 feet, built to water-surface, and 200 of the 300 feet reported in the last annual report as without superstructure has been completed. It is proposed during the ensuing season to have the superstructure of the remaining 100 feet completed, and to extend the breakwater 650 feet sub and superstructure, giving, by June 30, 1873, a complete breakwater 1,850 feet in length, extending to 30 feet of water. The effect of this structure on the harbor is now marked, and the beneficial influence of each addition is experienced at once. The original estimate for this breakwater was $385,129 58, and the length designed, 2,050 feet; $190,000 has been appropriated, which will complete 1,850 feet, leaving only 200 feet to complete the work as intended. Owing to the increasing importance of Marquette Harbor and the necessity of its better protection, it is recommended that the work be continued to the amount of the original estimate.

Amount on hand July 1, 1870........

$29,477 60 25, 000 00

Amount appropriated by act of July 11, 1870..
Amount appropriated by act of March 3, 1871.

60, 000 00

Amount expended during the fiscal year ending June 30,

1871 ....

Amount available July 1, 1871...

29, 459 63 85,017 91

Amount required for fiscal year ending June 30, 1873..... 100, 000 00

(See Appendix A 5.)

6. Menomonee Harbor, Michigan.-An appropriation for the improvement of this harbor was made by the act of March 3, 1871, and an examination of the locality at once undertaken to ascertain what changes, if any, had taken place since the summer of 1867. A project for improvement, consisting of a pile pier extending in a northeasterly direction to a depth of 15 feet water, in Green Bay, commencing at a point south of the center of the sand-point forming the north shore of the mouth of the river; this pier to constitute the permanent work of the improvement for the harbor, and to be extended inward, or connected with the south bank of the river, as experience or the rights of property-owners may hereafter determine.

[ocr errors]

A contract was entered into in June for the construction of the pier, and it is expected that at least 1,000 feet of it will be completed by the close of the present working season.

Amount appropriated by act of March 3, 1871....

Amount expended during the fiscal year ending June 30, 1871....

Amount available July 1, 1871..

Amount required for fiscal year ending June 30, 1873

(See Appendix A 6.)

$25,000 00

227 50 24, 772 50 25,000 00

7. Green Bay Harbor, Wisconsin.-The work at this harbor during the year has consisted in continuing the dredging south of Grassy Island so as to give a width of 200 feet, and straightening and deepening the area heretofore dredged; in revetting the channel through Grassy Island on the west side; cutting a channel 2,000 feet in length north of that island; extending the revetment on the east side 85 feet, and rip-rapping 450 feet on the east and 280 feet on the west side of the island, to a height of 18 inches above the water surface. It is proposed to dredge a channel 200 feet wide and 14 feet deep south of Grassy Island as far as the mouth of Fox River, and to widen the cut already made on the west side of the island.

The plan of improvement adopted has proved successful, and has secured a safe and commodious harbor at this point, which is of great benefit to the general commerce of the lakes. An examination of

the work shows very little change in the dredged channel.

Amount on hand July 1, 1870....

Amount appropriated by act of July 11, 1870

Amount appropriated by act of March 3, 1871.

Amount available July 1, 1871.

Amount expended during the fiscal year ending June 30, 1871....

Which will complete the work of improvement. (See Appendix A 7.)

$12, 420 68

17;500 00

17,500 00

28,103 89 19,316 79

8. Ahnepee Harbor, Lake Michigan, Wisconsin.-A survey of this harbor was made during the season of 1870, in pursuance of the second section of the act of July 11, 1870, and a plan for its improvement, with estimate of cost, submitted to Congress in January last. An appropriation was made for the improvement by the act of March 3, 1871, and the work contracted for as soon as the necessary arrangements could be perfected. Work under the contract is now progressing favorably. The officer in charge is of the opinion that 600 feet of pier will be completed by the close of the present working season. Amount appropriated by act of March 3, 1871

Amount expended during the fiscal year ending June 30, 1871...

Amount available July 1, 1871 ...........

Amount required for fiscal year ending June 30, 1873

[ocr errors][merged small]

$25,000 00

169 40

24, 830 60 50,000 00

9. Two Rivers, Wisconsin.-A survey was made of this locality, as directed by the second section of the act of July 11, 1870, and a plan for its improvement, with estimate of cost, was submitted to Congress in January last. By the act of March 3, 1871, the improvement was

provided for, and measures were at once taken to carry it out, to the extent of the appropriation. A contract was entered into in June for the construction of 400 feet of pile-pier on the east side, and 400 feet on the west side of the mouth of the river, and it is expected that the work contemplated will be completed during the present working

season.

Amount appropriated by act of March 3, 1871....

Amount expended during the fiscal year ending June 30, 1871....

Amount available July 1, 1871, and which will be absorbed by existing contracts

Amount required for fiscal year ending June 30, 1873 ...

(See Appendixes A 9 and A 22.)

....

$25,000 00

31 30

24,968 70

50,000 00

10. Manitowoc Harbor, Wisconsin.-During the year the north pier has been extended 128 feet, and the south pier 96 feet; in all, 7 cribs built to the water-surface. A further extension will be made this season of 96 feet to each of the piers, and superstructure will be built over the 7 cribs which were sunk last season. No further extension of the piers is needed at present, as there will be 14 feet of water at the mouth of the harbor on the completion of the present contract.

Amount on hand July 1, 1870....

$370 24

Amount appropriated by act of July 11, 1870.
Amount appropriated by act of March 3, 1871

Amount expended during the fiscal year ending June 30,

1871....

Amount available July 1, 1871.

(See Appendix A 10.)

20, 000 00

11,000 00

11,271 20

20,459 04

11. Sheboygan Harbor, Wisconsin.-During the past fiscal year superstructure was built over the four cribs which were constructed under contract June 23, 1869, in extension of the south pier, and two cribs, each 32 feet by 20 feet, have been constructed and sunk in position over the sites occupied by the two outer cribs of the south pier, broken and carried away by storms in the fall of 1869. Additional extensions will be made during the present working season of 128 feet to the south pier, and 320 feet to the north pier, together forming a total length of 448 feet of pier-work. The work at this harbor should be finished by placing a crib pier-head, 50 by 30 feet, at the extremity of each pier.

The work, which was built prior to 1860, needs repairing for a length of 600 feet, and 5,000 cubic yards of excavation is required in the channel.

Amount on hand July 1, 1870..

Amount appropriated by act of July 11, 1870..
Amount appropriated by act of March 3, 1871..

Amount expended during the fiscal year ending June 30,
1871...

Amount covered into Treasury under act of July 12, 1870
Amount required for fiscal year ending June 30, 1873 ......

(See Appendix A 11.)

$7,811 84

15,000 00

15, 600 00

7,170 85

1,554 29

28,000 00

« PreviousContinue »