Page images
PDF
EPUB

Cost of stone..
Cost of timber.
Cost of slabs.
Cost of piles...
Superintendence
Advertising.

$4,849 84 2,351 34

1,143 467

1,074 66

486 65

68 00

30, 937 64

Amount on hand July 1, 1870...

Appropriation approved July 11, 1870...
Appropriation approved March 3, 1871.
Received from sale of timber...

Less amount covered in Treasury of appropriation for repairs,

&c., by act approved July 12, 1870.

Amount expended during fiscal year..

Amount on hand July 1, 1871...

[blocks in formation]

During the present season it is proposed to finish both piers as shown in blue on accompanying sketch. This will give each pier a total length of 810 feet beyond the beach line.

It may be that the piers will have to be extended still farther if a bar forms again across the mouth of the channel. To do the dredging still necessary and properly ballasting the piers will require an additional appropriation of $10,000, which can be profitably expended during the fiscal year ending June 30, 1873.

White River is in the district of Michigan, and the nearest port of entry is Grand Haven. The nearest light-house is at Muskegon, twelve miles distant.

Abstract of bids received and opened August 27, 1870, for furnishing stone at White River Harbor, Michigan.

[blocks in formation]

List of vessels entered and cleared White River Harbor, Michigan, showing number, crews, and

Entered.

cargoes, during year 1870.

Cleared.

[blocks in formation]

B 6.

REPORT OF OPERATIONS AT THE HARBOR AT MUSKEGON, MICHIGAN.

The superstructure over the cribs built in 1869 was finished last season, and a crib 32 feet by 32 feet was placed as a pier-head to the north pier. Last spring another crib, 32 feet by 32 feet, was placed, extending the north pier 32 feet, and the north and south piers were repaired, and the south pier re-ballasted. Both piers had been seriously damaged by vessels running into them. The cost of the work was as follows: Labor on framing and repairs of cribs and superstructure, &c. $6, 955 84 Cost of stone..

Cost of timber

Cost of iron
Superintendence
Advertising

Amount on hand July 1, 1870 ...
Appropriation approved July 11, 1870
Appropriation approved March 3, 1871..

Amount expended during fiscal year.
Amount on hand July 1, 1871

4,059 84 2,193 55 494 15 1,121 28

205 50

15,030 16

$3,543 80 10, 000 00 15,000 00

28, 543 80 15,030 16

13, 513 64

This harbor is at present in good condition, and no new work is necessary. The slab-piers interior to the crib-piers are fast rotting away, and they should be replaced by pile-piers, thus utilizing the slabs now under water and in place. This work has already been recommended in previous reports, and will cost $28,000; 250 cords of stone are necessary to reballast the north pier, which will cost about $4,000. There will therefore be necessary for the fiscal year ending June 30, 1873, the sum of $18,500.

Muskegon is in the collection district of Michigan, and the nearest port of entry is Grand Haven, twelve miles south. It has a small lighthouse, with lights of the sixth order.

Abstract of bids received and opened March 31, 1871, for furnishing stone at Muskegon Harbor, Michigan.

[blocks in formation]

Statement of vessels entered and cleared Muskegon Harbor, Michigan, showing number, crews and cargoes during year 1870.

[blocks in formation]

REPORT OF OPERATIONS AT GRAND HAVEN HARBOR, MICHIGAN.

After due advertising and opening of proposals, August 27, 1870, contracts were awarded to Messrs. Peirce & Whaling for iron, to Messrs. G..P. Adams & Bro. for stone, and to T. Stewart White for all the remaining materials, and all the work of repairing the old railroad pier. Under this contract, 200 feet of repairs were completed, and the remaining 400 feet well under way. The detailed cost of the work was as follows:

11,734 feet white-oak piles, at 15 cents per foot
35,940 feet, board measure, pine timber, at $25 per M
3,112 feet, board measure, oak timber, at $45 per M
127.30 cords of stone, at $10 90
30 cords of stone, at $15..

$1,760 10 898 50

541.58 cords of slabs, at $2 25.

12,294 pounds of drift-bolts, at $3 65 per pound.

787 pounds of screw-bolts, at 476 per pound..

Driving piles, 3,829 feet, at 20 cents per foot.

Tearing away 500 feet old work, at $1 75 per foot..

[blocks in formation]

140 04 1,387 57 457 50 1,218 55

448 73

36 99

765 80

875 00

211 74

904 23

64 50

5.00

Use of scow two days, at $2 50 per day.
Labor...

Total.....

Amount on hand July 1, 1870..........
Appropriation approved July 12, 1870
Appropriation approved March 3, 1871..

Amount expended during fiscal year

Amount on hand July 1, 1871..

67 00

9, 241 25

$293 00 10, 000 00 6,000 00

16, 293 00

9, 241 25

7,051 75

During the present season the repairs to the old railroad pier will be completed, which will exhaust the amount on hand.

A pier-head should be built at the end of the present pier, which will cost $7,000.

I would again urge the building of a north pier, which will cost $200,000. Until this pier is built this harbor cannot be made one of refuge.

A great deal of re-ballasting of crib-pier is necessary, and some repairs to the timber work, which will cost about $5,300.

The long revetment interior to the railroad-pier, built in 1867, is in very bad repair, and I fear that a large portion of it will have to be rebuilt. It has been damaged by being used as a dock by vessels, by being run into by vessels not under control, and by being undermined by the current of the river, where it impinges against it.

At present prices the repairs of this interior work (shown on accompanying tracing from A to B) would cost about $36,000. The urgency of the repairs is as great as that which required its building in 1867. On the accompanying tracing the blue lines show work in progress, and red lines new work recommended under future appropriations.

Abstract of bids received and opened August 27, 1870, for improving harbor at Grand Haven,

Michigan.

[blocks in formation]

Abstract of contracts for material and work for improving harbor at Grand Haven, Michigan.

[blocks in formation]

cts.

cts.

cts.

6.50 20 $1 75

3.75
5. 25
3.65 4.70

[blocks in formation]
[blocks in formation]

cts. cts.

20 $2.25

[blocks in formation]

Statement of vessels entered Grand Haven Harbor, Michigan, showing number, tonnage, crews, and cargoes, during the year 1870.

[blocks in formation]

Statement of vessels cleared Grand Haven Harbor, Michigan, showing the number, tonnage, crews, and cargoes, during the year 1870.

[blocks in formation]

8. REPORT OF THE WORK OF IMPROVING THE HARBOR AT BLACK LAKE,

MICHIGAN.

A crib, 32 feet square in plan, was placed last autumn as a pier-head to the north pier. It was only built to the water's surface, and left to properly bed itself during the winter. There was also built 100 feet of crib-work, extending the south pier inward to prevent a breach. By a reference to the accompanying sketch, it will be seen that a further breach is threatened on the south side of the harbor, rendering imperatively necessary the work now being done, (shown in blue.)

The work of first half of fiscal year was done by hired labor. After due advertising and opening of bids on August 27, 1870, contracts were awarded to the lowest bidders, Willard B. Johnson, for furnishing pine timber; John Roost for furnishing stone and slabs, and Messrs. Peirce & Whaling for furnishing iron. On May 5, 1871, after due advertising and opening of bids, contracts were awarded to Messrs. Peirce & Whaling for furnishing the iron, and to Messrs. Uriah Culbert & Co. for fur

« PreviousContinue »