Professional Construction ManagementThe subjects covered in this book include those normally studied in an introductory overview course on construction management, and there is enough depth and added material to serve as the basis for a more advanced course, focusing on organizational and contractual approaches to project management, and the related planning and control systems. This new edition strengthens its coverage of the business aspects of the industry, with a section devoted solely to the business methods in professional construction management. The text's practical in-depth approach to the major engineering and management techniques appeals to both students and practitioners alike. Copyright © Libri GmbH. All rights reserved. |
From inside the book
Results 1-3 of 31
Page 173
0330 CONCRETE PLACING FOR FOUNDATION EST FINISH : 08/01/83 QUANTITIES ACT FINISH : UNIT COSTS : CRW . 0320 CONCRETE RE - STEEL FOR WALLS LB 29 21 9 30 70 % 1 3.5 % $ 39400 $ 31700 $ 13610 $ 45310 70 % $ 5910 15.0 % HIGH 82400 74410 ...
0330 CONCRETE PLACING FOR FOUNDATION EST FINISH : 08/01/83 QUANTITIES ACT FINISH : UNIT COSTS : CRW . 0320 CONCRETE RE - STEEL FOR WALLS LB 29 21 9 30 70 % 1 3.5 % $ 39400 $ 31700 $ 13610 $ 45310 70 % $ 5910 15.0 % HIGH 82400 74410 ...
Page 177
He must assess quantities not only of the contract materials reflected in the drawings , but also of the temporary materials , such as formwork for concrete and temporary plant . The latter estimates , in turn , require that the ...
He must assess quantities not only of the contract materials reflected in the drawings , but also of the temporary materials , such as formwork for concrete and temporary plant . The latter estimates , in turn , require that the ...
Page 293
overhead incurred in requisitioning , soliciting , and evaluating quotations , and in issuing purchase orders ; ( 2 ) the actual materials prices obtained through effective negotiation , variations in unit costs with quantities , the ...
overhead incurred in requisitioning , soliciting , and evaluating quotations , and in issuing purchase orders ; ( 2 ) the actual materials prices obtained through effective negotiation , variations in unit costs with quantities , the ...
What people are saying - Write a review
We haven't found any reviews in the usual places.
Contents
Professional Construction Management in | 3 |
MANAGEMENT IN PRACTICE | 15 |
Development and Organization of Projects | 18 |
Copyright | |
32 other sections not shown
Other editions - View all
Common terms and phrases
acceptance activities actual additional Agreement alternative amount applicable approach approval Architect associated award basic become bidders budget building changes chapter chart claims Company completion concept concrete considerations contract Contractor cost detail determine developed direct documents drawings economic effect engineering equipment estimate evaluation example facilities factors field Figure final finish firms floor important individual industry inspection involved labor major materials methods needed negotiated objectives operations organization overall Owner packages payment percent performance period phase planning practices preliminary prepared problems procedures procurement productivity professional construction manager progress proposed quantities reasonable reports responsibilities safety savings schedule shows Special specifications standard Structural Subcontractor testing tion Trade unassigned union unit warehouse