Professional Construction ManagementMcGraw-Hill, 1984 - 540 pages The subjects covered in this book include those normally studied in an introductory overview course on construction management, and there is enough depth and added material to serve as the basis for a more advanced course, focusing on organizational and contractual approaches to project management, and the related planning and control systems. This new edition strengthens its coverage of the business aspects of the industry, with a section devoted solely to the business methods in professional construction management. The text's practical in-depth approach to the major engineering and management techniques appeals to both students and practitioners alike. Copyright © Libri GmbH. All rights reserved. |
From inside the book
Results 1-3 of 83
Page 96
... drawings and identifies drawings to be included as reference drawings . 6 Before the manager incorporates the package into the bidding docu- ments , the designer reviews the entire scope of the work package as just described . Owner ...
... drawings and identifies drawings to be included as reference drawings . 6 Before the manager incorporates the package into the bidding docu- ments , the designer reviews the entire scope of the work package as just described . Owner ...
Page 160
... drawings . Two of the required drawings describe the electrical instrumentation and controls for a crushing and grinding circuit . Since it is similar to one done before , the engineering budget provided for it as follows : 80 design ...
... drawings . Two of the required drawings describe the electrical instrumentation and controls for a crushing and grinding circuit . Since it is similar to one done before , the engineering budget provided for it as follows : 80 design ...
Page 412
Donald S. Barrie, Boyd C. Paulson. 3. Engineering Drawings The following drawings were required for the project : Plot Plan and Utility Plan Drawing SI - 1 Drawing A - 1 Drawing A - 2 Drawing A - 3 Drawing PH - 1 Drawing E - 1 Foundation ...
Donald S. Barrie, Boyd C. Paulson. 3. Engineering Drawings The following drawings were required for the project : Plot Plan and Utility Plan Drawing SI - 1 Drawing A - 1 Drawing A - 2 Drawing A - 3 Drawing PH - 1 Drawing E - 1 Foundation ...
Contents
Professional Construction Management in | 3 |
MANAGEMENT IN PRACTICE | 15 |
Development and Organization of Projects | 18 |
Copyright | |
34 other sections not shown
Other editions - View all
Common terms and phrases
activities activity x actual Agreement alternative applicable approach approval Architect award bar chart basic bid packages bidders budget building change orders Chapter completion concept concrete construction contracts construction cost Construction Manager's construction project contract packages contractor control system cost code cost engineering critical path Critical Path Method curve design-construct detail developed documents drawings earthwork economic equipment evaluation example facilities factors fair-cost estimate field construction manager Figure finish firms Guaranteed Maximum Price home office HVAC important inspection kg/cm² labor lump-sum materials ment methods Mountaintown Warehouse negotiated operations organization overall owner payment percent performance phased construction program plans and specifications prepared procedures productivity professional construction manager progress project cost Project Manager proposed quality control quantities reports responsibilities safety scope standard Structural steel subcontractors summary tion Total unassigned unit utilities Value Engineering