Professional Construction ManagementThe subjects covered in this book include those normally studied in an introductory overview course on construction management, and there is enough depth and added material to serve as the basis for a more advanced course, focusing on organizational and contractual approaches to project management, and the related planning and control systems. This new edition strengthens its coverage of the business aspects of the industry, with a section devoted solely to the business methods in professional construction management. The text's practical in-depth approach to the major engineering and management techniques appeals to both students and practitioners alike. Copyright © Libri GmbH. All rights reserved. |
From inside the book
Results 1-3 of 30
Page 74
Recom- mendation regarding acceptance will be prepared by the CM Project Manager . 6. Review , modify , or approve all Contractor Monthly Progress Pay- ment Reports , and forward them to the Owner's Project Manager for approval and ...
Recom- mendation regarding acceptance will be prepared by the CM Project Manager . 6. Review , modify , or approve all Contractor Monthly Progress Pay- ment Reports , and forward them to the Owner's Project Manager for approval and ...
Page 115
Final Acceptance Basic documentation for acceptance of contract work depends somewhat upon state law and individual preference , but will generally include the following : Notice of Completion This form states that all work under the ...
Final Acceptance Basic documentation for acceptance of contract work depends somewhat upon state law and individual preference , but will generally include the following : Notice of Completion This form states that all work under the ...
Page 118
Field Transmittal Memorandum A " Field Transmittal Memorandum " ( FTM ) is useful in all field contract correspondence , transmittals , instructions , or other communications with the Contract Completion and Acceptance Certificate This ...
Field Transmittal Memorandum A " Field Transmittal Memorandum " ( FTM ) is useful in all field contract correspondence , transmittals , instructions , or other communications with the Contract Completion and Acceptance Certificate This ...
What people are saying - Write a review
We haven't found any reviews in the usual places.
Contents
Professional Construction Management in | 3 |
MANAGEMENT IN PRACTICE | 15 |
Development and Organization of Projects | 18 |
Copyright | |
32 other sections not shown
Other editions - View all
Common terms and phrases
acceptance activities actual additional Agreement alternative amount applicable approach approval Architect associated award basic become bidders budget building changes chapter chart claims Company completion concept concrete considerations contract Contractor cost detail determine developed direct documents drawings economic effect engineering equipment estimate evaluation example facilities factors field Figure final finish firms floor important individual industry inspection involved labor major materials methods needed negotiated objectives operations organization overall Owner packages payment percent performance period phase planning practices preliminary prepared problems procedures procurement productivity professional construction manager progress proposed quantities reasonable reports responsibilities safety savings schedule shows Special specifications standard Structural Subcontractor testing tion Trade unassigned union unit warehouse