Handbook of Construction Management and OrganizationVan Nostrand Reinhold, 1973 - 660 pages USA. Manual of and guide to business organization and management techniques for the construction industry - provides advice on the basics of contracting, bidding, financial management, equipment maintenance, network analysis, cost accounting, computerization, labour relations, occupational safety, public relations, taxation, etc. Flow charts, graphs, photographs, references and statistical tables. |
From inside the book
Results 1-3 of 91
Page 137
... Facilities Most machine owners have some type of equipment service facilities . Normally these are permanent structures located near the home offices . A small contractor may use his off- season machine storage building for limited ...
... Facilities Most machine owners have some type of equipment service facilities . Normally these are permanent structures located near the home offices . A small contractor may use his off- season machine storage building for limited ...
Page 139
... Facility needs vary with each construction project . Nevertheless , a number of basic requirements are valid for all on - site facilities : Site Selecting the site for the service shop is an integral part of the total operational plan ...
... Facility needs vary with each construction project . Nevertheless , a number of basic requirements are valid for all on - site facilities : Site Selecting the site for the service shop is an integral part of the total operational plan ...
Page 140
... Facility Under some conditions , permanent service facilities at the construction company's home base may be a worthwhile investment . Not only should these be matched to present equipment needs , but they should have a flexible layout ...
... Facility Under some conditions , permanent service facilities at the construction company's home base may be a worthwhile investment . Not only should these be matched to present equipment needs , but they should have a flexible layout ...
Other editions - View all
Common terms and phrases
accounting activities actual costs additional agreement AMOUNT UNIT COST application bank basic basis benefits bond BROWN'S FERRY changes charges cofferdam complete concrete contract contractor COST AMOUNT UNIT detail determined developed diagram Diffusion chamber DIRECT COST employees equipment excavation expense facilities factor FICTITIOUS FOR ILLUSTRATION field Figure functions historical cost home office income industry Install involved job cost joint venture labor loan loss machine maintenance materials ment method Morrison-Knudsen necessary operations organization overhead owner payment payroll percent performance period personnel preventive maintenance procedures profit project engineer project manager punched cards purchase quantities rates records rental repair reports result Riprap schedule subcontractors subnetwork supplies surety surety bond Target Estimate tion tractor underwriter UNIT COST AMOUNT usually wage