Handbook of Construction Management and OrganizationVan Nostrand Reinhold, 1973 - 660 pages USA. Manual of and guide to business organization and management techniques for the construction industry - provides advice on the basics of contracting, bidding, financial management, equipment maintenance, network analysis, cost accounting, computerization, labour relations, occupational safety, public relations, taxation, etc. Flow charts, graphs, photographs, references and statistical tables. |
From inside the book
Results 1-3 of 91
Page 222
... [ Concrete Form Cost Report ] As mentioned with re- spect to the monthly report under this title , the matter of cost of forms for concrete is one of the largest subsidiary items for which detailed cost information is desired . The final ...
... [ Concrete Form Cost Report ] As mentioned with re- spect to the monthly report under this title , the matter of cost of forms for concrete is one of the largest subsidiary items for which detailed cost information is desired . The final ...
Page 273
... concrete placing . Summary of Concrete Cost A format for summarizing the cost for a given bid item on a mass concrete job is shown in Figure 14-26-8 . It utilizes the elements of cost and production discussed earlier and adds other ...
... concrete placing . Summary of Concrete Cost A format for summarizing the cost for a given bid item on a mass concrete job is shown in Figure 14-26-8 . It utilizes the elements of cost and production discussed earlier and adds other ...
Page 474
... concrete form costs , and ( c ) Extension of concrete item costs . ( a ) Wage Rate Program The wage rate program for computer is fully described in the foregoing . It is men- tioned here only to emphasize that the routine extensions ...
... concrete form costs , and ( c ) Extension of concrete item costs . ( a ) Wage Rate Program The wage rate program for computer is fully described in the foregoing . It is men- tioned here only to emphasize that the routine extensions ...
Other editions - View all
Common terms and phrases
accounting activities actual costs additional agreement AMOUNT UNIT COST application bank basic basis benefits bond BROWN'S FERRY changes charges cofferdam complete concrete contract contractor COST AMOUNT UNIT detail determined developed diagram Diffusion chamber DIRECT COST employees equipment excavation expense facilities factor FICTITIOUS FOR ILLUSTRATION field Figure functions historical cost home office income industry Install involved job cost joint venture labor loan loss machine maintenance materials ment method Morrison-Knudsen necessary operations organization overhead owner payment payroll percent performance period personnel preventive maintenance procedures profit project engineer project manager punched cards purchase quantities rates records rental repair reports result Riprap schedule subcontractors subnetwork supplies surety surety bond Target Estimate tion tractor underwriter UNIT COST AMOUNT usually wage