shall be paid into, reserved, and appropriated as a part of the reclamation fund created by the Act of Congress known as the Reclamation Act, approved June 17, 1902; and 371⁄2 per centum of the charges arising from licenses hereunder for the occupancy and use of national forests and public lands from development within the boundaries of any State shall be paid by the Secretary of the Treasury to such State; and 50 per centum of the charges arising from all other licenses hereunder is hereby reserved and appropriated as a special fund in the Treasury to be expended under the direction of the Secretary of War in the maintenance and operation of dams and other navigation structures owned by the United States or in the construction, maintenance, or operation of headwater or other improvements of navigable waters of the United States. The proceeds of charges made by the Commission for the purpose of reimbursing the United States for the costs of the administration of this Part shall be paid into the Treasury of the United States and credited. to miscellaneous receipts.

"(b) In case of delinquency on the part of any licensee in the payment of annual charges a penalty of 5 per centum of the total amount so delinquent may be added to the total charges which shall apply for the first month or part of month so delinquent with an additional penalty of 3 per centum for each subsequent month until the total of the charges and penalties are paid or until the license is canceled and the charges and penalties satisfied in accordance with law."

SEC. 209. Section 18 of the Federal Water Power Act, as amended, is amended to read as follows:

"SEC. 18. The Commission shall require the construction, maintenance, and operation by a licensee at its own expense of such lights and signals as may be directed by the Secretary of War, and such fishways as may be prescribed by the Secretary of Commerce. The operation of any navigation facilities which may be constructed as a part of or in connection with any dam or diversion structure built under the provisions of this Act, whether at the expense of a licensee hereunder or of the United States, shall at all times be controlled by such reasonable rules and regulations in the interest of navigation, including the control of the level of the pool caused by such dam or diversion structure as may be made from time to time by the Secretary of War; and for willful failure to comply with any such rule or regulation such licensee shall be deemed guilty of a misdemeanor, and upon conviction thereof shall be punished as provided in section 316 hereof."

SEC. 210. Section 23 of the Federal Water Power Act, as amended, is amended to read as follows:

"SEC. 23. (a) The provisions of this Part shall not be construed as affecting any permit or valid existing right-of-way heretofore granted or as confirming or otherwise affecting any claim, or as affecting any authority heretofore given pursuant to law, but any person, association, corporation, State, or municipality holding or possessing such permit, right-of-way, or authority may apply for a license hereunder, and upon such application the Commission may issue to any such applicant a license in accordance with the provisions of this Part and in such case the provisions of this Act

S

shall apply to such applicant as a licensee hereunder: Provided, That when application is made for a license under this section for a project or projects already constructed the fair value of said project or projects determined as provided in this section, shall for the purposes of this Part and of said license be deemed to be the amount to be allowed as the net investment of the applicant in such project or projects as of the date of such license, or as of the date of such determination, if license has not been issued. Such fair value shall be determined by the Commission after notice and opportunity for hearing.

or

(b) It shall be unlawful for any person, State, or municipality, for the purpose of developing electric power, to construct, operate, or maintain any dam, water conduit, reservoir, power house, or other works incidental thereto across, along, or in any of the navigable waters of the United States, or upon any part of the public lands or reservations of the United States (including the Territories), utilize the surplus water or water power from any Government dam, except under and in accordance with the terms of a permit or valid existing right-of-way granted prior to June 10, 1920, or a license granted pursuant to this Act. Any person, association, corporation, State, or municipality intending to construct a dam or other project works across, along, over, or in any stream or part thereof, other than those defined herein as navigable waters, and over which Congress has jurisdiction under its authority to regulate commerce with foreign nations and among the several States shall before such construction file declaration of such intention with the Commission, whereupon the Commission shall cause immediate investigation of such proposed construction to be made, and if upon investigation it shall find that the interests of interstate or foreign commerce would be affected by such proposed construction, such person, association, corporation, State, or municipality shall not construct, maintain, or operate such dam or other project works until it shall have applied for and shall have received a license under the provisions of this Act. If the Commission shall not so find, and if no public lands or reservations are affected, permission is hereby granted to construct such dam or other project works in such stream upon compliance with State laws."

SEC. 211. Section 24 of the Federal Water Power Act, as amended, is amended to read as follows:

"SEC. 24. Any lands of the United States included in any proposed project under the provisions of this Part shall from the date of filing of application therefor be reserved from entry, location, or other disposal under the laws of the United States until otherwise directed by the Commission or by Congress. Notice that such application has been made, together with the date of filing thereof and a description of the lands of the United States affected thereby, shall be filed in the local land office for the district in which such lands are located. Whenever the Commission shall determine that the value of any lands of the United States so applied for, or heretofore or hereafter reserved or classified as power sites, will not be injured or destroyed for the purposes of power development by location, entry, or selection under the public land laws, the Secretary of the Interior, upon notice of such determination, shall declare

87-521 O 739

such lands open to location, entry, or selection, for such purpose or purposes and under such restrictions as the Commission may determine, subject to and with a reservation of the right of the United States or its permittees or licensees to enter upon, occupy, and use any part or all of said lands necessary, in the judgment of the Commission, for the purposes of this Part, which right shall be expressly reserved in every patent issued for such lands; and no claim or right to compensation shall accrue from the occupation or use of any of said lands for said purposes. The United States or any licensee for any such lands hereunder may enter thereupon for the purposes of this Part, upon payment of any damages to crops, buildings, or other improvements caused thereby to the owner thereof, or upon giving a good and sufficient bond to the United States for the use and benefit of the owner to secure the payment of such damages as may be determined and fixed in an action brought upon the bond in a court of competent jurisdiction, said bond to be in the form prescribed by the Commission: Provided, That locations, entries, selections, or filings heretofore made for lands reserved as water-power sites, or in connection with water-power development, or electrical transmission may proceed to approval or patent under and subject to the limitations and conditions in this section contained.

SEC. 212. Sections 1 to 29, inclusive, of the Federal Water Power Act, as amended, shall constitute Part I of that Act, and sections 25 and 30 of such Act, as amended, are repealed: Provided, That nothing in that Act, as amended, shall be construed to repeal or amend the provisions of the amendment to the Federal Water Power Act approved March 3, 1921 (41 Stat. 1353), or the provisions of any other Act relating to national parks and national monuments. SEC. 213. The Federal Water Power Act, as amended, is further amended by adding thereto the following parts:

“PART II—REGULATION OF ELECTRIC UTILITY COMPANIES ENGAGED IN INTERSTATE COMMERCE

66

DECLARATION OF POLICY; APPLICATION OF PART; DEFINITIONS "SECTION 201. (a) It is hereby declared that the business of transmitting and selling electric energy for ultimate distribution to the public is affected with a public interest, and that Federal regulation of matters relating to generation to the extent provided in this Part and the Part next following and of that part of such business which consists of the transmission of electric energy in interstate commerce and the sale of such energy at wholesale in interstate commerce is necessary in the public interest, such Federal regulation, however, to extend only to those matters which are not subject to regulation by the States.

(b) The provisions of this Part shall apply to the transmission of electric energy in interstate commerce and to the sale of electric energy at wholesale in interstate commerce, but shall not apply to any other sale of electric energy or deprive a State or State commission of its lawful authority now exercised over the exportation of hydroelectric energy which is transmitted across a State line. The Commission shall have jurisdiction over all facilities for such transmission or sale of electric energy, but shall not have jurisdiction,

except as specifically provided in this Part and the Part next following, over facilities used for the generation of electric energy or over facilities used in local distribution or only for the transmission of electric energy in intrastate commerce, or over facilities for the transmission of electric energy consumed wholly by the transmitter.

(c) For the purpose of this Part, electric energy shall be held to be transmitted in interstate commerce if transmitted from a State and consumed at any point outside thereof; but only insofar as such transmission takes place within the United States.

"(d) The term "sale of electric energy at wholesale' when used in this Part means a sale of electric energy to any person for resale. "(e) The term 'public utility' when used in this Part or in the Part next following means any person who owns or operates facilities subject to the jurisdiction of the Commission under this Part. "(f) No provision in this Part shall apply to, or be deemed to include, the United States, a State or any political subdivision of a State, or any agency, authority, or instrumentality of any one or more of the foregoing, or any corporation which is wholly owned, directly or indirectly, by any one or more of the foregoing, or any officer, agent, or employee of any of the foregoing acting as such in the course of his official duty, unless such provision makes specific reference thereto.

INTERCONNECTION AND COORDINATION OF FACILITIES; EMERGENCIES; TRANSMISSION TO FOREIGN COUNTRIES

"Src. 202. (a) For the purpose of assuring an abundant supply of electric energy throughout the United States with the greatest possible economy and with regard to the proper utilization and conservation of natural resources, the Commission is empowered and directed to divide the country into regional districts for the voluntary interconnection and coordination of facilities for the generation, transmission, and sale of electric energy, and it may at any time thereafter, upon its own motion or upon application, make such modifications thereof as in its judgment will promote the public interest. Each such district shall embrace an area which, in the judgment of the Commission, can economically be served by such interconnected and coordinated electric facilities. It shall be the duty of the Commission to promote and encourage such interconnection and coordination within each such district and between such districts. Before establishing any such district and fixing or modifying the boundaries thereof the Commission shall give notice to the State commission of each State situated wholly or in part within such district, and shall afford each such State commission reasonable opportunity to present its views and recommendations, and shall receive and consider such views and recommendations.

"(b) Whenever the Commission, upon application of any State commission or of any person engaged in the transmission or sale of electric energy, and after notice to each State commission and public utility affected and after opportunity for hearing, finds such action necessary or appropriate in the public interest it may by order direct a public utility (if the Commission finds that no undue burden will be placed upon such public utility thereby) to establish physical

connection of its transmission facilities with the facilities of one or more other persons engaged in the transmission or sale of electric energy, to sell energy to or exchange energy with such persons: Provided, That the Commission shall have no authority to compel the enlargement of generating facilities for such purposes, nor to compel such public utility to sell or exchange energy when to do so would impair its ability to render adequate service to its customers. The Commission may prescribe the terms and conditions of the arrangement to be made between the persons affected by any such order, including the apportionment of cost between them and the compensation or reimbursement reasonably due to any of them.

"(c) During the continuance of any war in which the United States is engaged, or whenever the Commission determines that an emergency exists by reason of a sudden increase in the demand for electric energy, or a shortage of electric energy or of facilities for the generation or transmission of electric energy, or of fuel or water for generating facilities, or other causes, the Commission shall have authority, either upon its own motion or upon complaint, with or without notice, hearing, or report, to require by order such temporary connections of facilities and such generation, delivery, interchange, or transmission of electric energy as in its judgment will best meet the emergency and serve the public interest. If the parties affected by such order fail to agree upon the terms of any arrangement between them in carrying out such order, the Commission, after hearing held either before or after such order takes effect, may prescribe by supplemental order such terms as it finds to be just and reasonable, including the compensation or reimbursement which should be paid to or by any such party.

"(d) During the continuance of any emergency requiring immediate action, any person engaged in the transmission or sale of electric energy and not otherwise subject to the jurisdiction of the Commission may make such temporary connections with any public utility subject to the jurisdiction of the Commission or may construct such temporary facilities for the transmission of electric energy in interstate commerce as may be necessary or appropriate to meet such emergency, and shall not become subject to the jurisdiction of the Commission by reason of such temporary connection or temporary construction: Provided, That such temporary connection shall be discontinued or such temporary construction removed or otherwise disposed of upon the termination of such emergency: Provided further, That upon approval of the Commission permanent connections for emergency use only may be made hereunder.

"(e) After six months from the date on which this Part takes effect, no person shall transmit any electric energy from the United States to a foreign country without first having secured an order of the Commission authorizing it to do so. The Commission shall issue such order upon application unless, after opportunity for hearing, it finds that the proposed transmission would impair the sufficiency of electric supply within the United States or would impede or tend to impede the coordination in the public interest of facilities subject to the jurisdiction of the Commission. The Commission may by its order grant such application in whole or in part, with such modifications and upon such terms and conditions

« PreviousContinue »