Professional Construction ManagementMcGraw-Hill Education, 1992 - 577 pages The subjects covered in this book include those normally studied in an introductory overview course on construction management, and there is enough depth and added material to serve as the basis for a more advanced course, focusing on organizational and contractual approaches to project management, and the related planning and control systems. This new edition strengthens its coverage of the business aspects of the industry, with a section devoted solely to the business methods in professional construction management. The text's practical in-depth approach to the major engineering and management techniques appeals to both students and practitioners alike. |
From inside the book
Results 1-3 of 69
Page 224
... shown by w on Figure 11-7b . This is the number that should be used for estimating . Note that if the number of units is greater , as shown by n ' , the average worker - hours per unit should be less , as shown by w ' . It is therefore ...
... shown by w on Figure 11-7b . This is the number that should be used for estimating . Note that if the number of units is greater , as shown by n ' , the average worker - hours per unit should be less , as shown by w ' . It is therefore ...
Page 256
... ( shown by the open plan bar ) and that 60 percent of the time ( 3 months out of 5 ) has elapsed by the reporting period . However , the shaded bar reports that only 50 percent of the physical work in the activity has been completed . On ...
... ( shown by the open plan bar ) and that 60 percent of the time ( 3 months out of 5 ) has elapsed by the reporting period . However , the shaded bar reports that only 50 percent of the physical work in the activity has been completed . On ...
Page 261
... shown by curves P and R respectively on Figure 12-8c . Cash Flows Cash flows may be shown graphically by plotting one progress curve for expenditures on the same graph with a second curve for income . A third curve representing the ...
... shown by curves P and R respectively on Figure 12-8c . Cash Flows Cash flows may be shown graphically by plotting one progress curve for expenditures on the same graph with a second curve for income . A third curve representing the ...
Contents
Construction Industry and Practice | 3 |
Development and Organization of Projects | 14 |
Applications and Requirements for Management | 41 |
Copyright | |
24 other sections not shown
Other editions - View all
Common terms and phrases
activities actual AGC DOCUMENT Agreement alternative applicable arbitration Architect Architect/Engineer ASCE associated Associated General Contractors award bar chart basic bid packages bidders budget Change Order chapter claims completion concept concrete construction contracts Construction Cost Construction Division construction industry Construction Manager's construction projects Contract Documents control system cost code critical path Critical Path Method delays design-construct detail developed Direct Cost dispute drawings economic effect employees equipment evaluation example factors fair-cost estimate Figure firms Guaranteed Maximum Price home office HVAC impact labor liability major Masterformat materials methods negotiated normally open-shop operations organization overall owner parties payment percent performance preliminary prepared procedures procurement productivity professional construction manager program management progress Project Manager quality control responsibility risk schedule scope standard Structural Structural steel Subcontractor summary tion Total union unit utilized value engineering