Professional Construction ManagementThe subjects covered in this book include those normally studied in an introductory overview course on construction management, and there is enough depth and added material to serve as the basis for a more advanced course, focusing on organizational and contractual approaches to project management, and the related planning and control systems. This new edition strengthens its coverage of the business aspects of the industry, with a section devoted solely to the business methods in professional construction management. The text's practical in-depth approach to the major engineering and management techniques appeals to both students and practitioners alike. |
From inside the book
Results 1-3 of 66
Page 191
0320 CONCRETE RE - STEEL FOR FOUNDATION EST START : 06/09/83 DURATION : ACT START : 06/12/83 COSTS : EST FINISH : 07/18/83 QUANTITIES : ACT FINISH : 1 UNIT COSTS : CPF . 0330 CONCRETE PLACING FOR FOUNDATION EST START : 06/16/83 DURATION ...
0320 CONCRETE RE - STEEL FOR FOUNDATION EST START : 06/09/83 DURATION : ACT START : 06/12/83 COSTS : EST FINISH : 07/18/83 QUANTITIES : ACT FINISH : 1 UNIT COSTS : CPF . 0330 CONCRETE PLACING FOR FOUNDATION EST START : 06/16/83 DURATION ...
Page 281
The following rules define the algorithm for the backward pass : 1 The latest allowable finish ( LF ) of all activities with no followers is equal to the target project completion time ( T ) . 2 The latest allowable finish time ( LF ) ...
The following rules define the algorithm for the backward pass : 1 The latest allowable finish ( LF ) of all activities with no followers is equal to the target project completion time ( T ) . 2 The latest allowable finish time ( LF ) ...
Page 496
Total Construction Cost - Building Finish EXAMPLE BID PACKAGE The example site earthwork bid package has. Unit Cost Quantity Labor Mat'l Description Labor Material Total Building Finish , cont'd . Furnishings & Equipment Adjustable Dock ...
Total Construction Cost - Building Finish EXAMPLE BID PACKAGE The example site earthwork bid package has. Unit Cost Quantity Labor Mat'l Description Labor Material Total Building Finish , cont'd . Furnishings & Equipment Adjustable Dock ...
What people are saying - Write a review
We haven't found any reviews in the usual places.
Contents
Construction Industry and Practice | 3 |
Development and Organization of Projects | 14 |
Applications and Requirements for Management | 41 |
Copyright | |
24 other sections not shown
Other editions - View all
Common terms and phrases
acceptance activities actual additional Agreement alternative amount applicable approach Architect associated award basic bidders building changes chapter claims companies compared completion concept concrete continue contract Contract Documents contractor cost delays detail determine developed direct discussed Documents drawings economic effect engineering equipment estimate evaluation example factors field Figure final finish firms force functional impact important increase individual industry involved labor limited major materials methods negotiated normally objectives obtain operations organization overall owner packages parties payment percent performance period phase planning practices prepared problems procedures procurement productivity professional construction manager progress proposed reasonable representative responsibility result risk safety schedule scope selection shows similar Special specifications standard Structural Subcontractor union unit utilized