| United States. Court of Claims, Audrey Bernhardt - 1968 - 922 pages
...writing accordingly. Any claim by the Contractor for adjustment under this clause must be asserted within 30 days from the date of receipt by the Contractor...clause of this contract entitled "Disputes." However, nothing in this clause shall excuse the Contractor from proceeding with the contract as changed. *****... | |
| United States. Court of Claims, Audrey Bernhardt - 1959 - 1028 pages
...in writing within 30 days from the date of receipt by the Contractor of the notification of extra or change : Provided, however, That the Contracting Officer,...upon any such claim asserted at any time prior to the date of final settlement of the contract. If the parties fail to agree upon the adjustment to be... | |
| 1969 - 752 pages
...hourly rates, (ill) delivery schedule, and (Iv) In such other provisions of the contract as may be so affected, and the contract shall be modified In writing...to any adjustment shall be a dispute concerning a question of fact within the meaning of the "Disputes" clause of this contract. However, nothing In... | |
| 1974 - 788 pages
...writing accordingly. Any claim by the Contractor ior adjustment under this clause must be asserted within 30 days from the date of receipt by the Contractor...clause of this contract entitled "Disputes." However, nothing in this clause shall excuse the Contractor from proceeding with the contract as changed. §... | |
| 1965 - 1168 pages
...Any claim by the Contractor for adjustment under this clause must be asserted within sixty (60) days from the date of receipt by the Contractor of the...clause of this contract entitled "Disputes." However, nothing In this clause shall excuse the Contractor from proceeding with the contract as changed. §... | |
| 1976 - 864 pages
...estimated cost or delivery schedule, or both, and (b) In such other provisions of the contract as may be so affected, and the contract shall be modified In writing...any time prior to final payment under this contract. Where the cost of property made obsolete or excess as a result of a change Is Included In the Contractor's... | |
| 1978 - 880 pages
...contract price or time of performance, or both, and (it) in such provisions of the contract as may be so affected, and the contract shall be modified in writing...any time prior to final payment under this contract. Where the cost of property made obsolete or excess as a result of a change is included in the Contractor's... | |
| 1979 - 1186 pages
...to be paid to the Contractor; and (iii) in such other provisions of the contract as may be affected, contract shall be modified in writing accordingly....prior to final payment under this contract Failure to 7-404.1 ARMED SERVICES PROCUREMENT REGULATION 7:267 CONTRACT CLAUSES AND SOLICITATION PROVISIONS agree... | |
| 1977 - 944 pages
...price or time of performance, or both, and (11) In such other provisions of the contract as may be so affected, and the contract shall be modified In writing...upon any such claim asserted at any time prior to flnal payment under this contract. Failure to agree to any adjustment shall be a dispute concerning... | |
| 1974 - 1020 pages
...for adjustment under this clause must be asserted within sixty (60) days from the date of receipt b; the Contractor of the notification of change : Provided,...clause of this contract entitled "Disputes." However, nothing In this clause shall excuse the Contractor from proceeding with the contract as changed. In... | |
| |