Professional Construction ManagementThe subjects covered in this book include those normally studied in an introductory overview course on construction management, and there is enough depth and added material to serve as the basis for a more advanced course, focusing on organizational and contractual approaches to project management, and the related planning and control systems. This new edition strengthens its coverage of the business aspects of the industry, with a section devoted solely to the business methods in professional construction management. The text's practical in-depth approach to the major engineering and management techniques appeals to both students and practitioners alike. |
From inside the book
Results 1-3 of 52
Page 105
The owner or his representative must strike a reasonable balance to stimulate high interest while assuring reasonable com- petition . Six to eight bidders is normally about right . With prequalification , the award can almost always be ...
The owner or his representative must strike a reasonable balance to stimulate high interest while assuring reasonable com- petition . Six to eight bidders is normally about right . With prequalification , the award can almost always be ...
Page 456
The contractor is entitled to the reasonable additional costs attributable to the delay as well as an extension of the ... to perform more work during a given period of time than that which was reasonably initially contemplated .
The contractor is entitled to the reasonable additional costs attributable to the delay as well as an extension of the ... to perform more work during a given period of time than that which was reasonably initially contemplated .
Page 522
3.11 The Owner shall furnish , prior to commencing work and at such future times as may be requested , reasonable evidence satisfactory to the Construction Manager that sufficient funds are available and committed for the entire cost of ...
3.11 The Owner shall furnish , prior to commencing work and at such future times as may be requested , reasonable evidence satisfactory to the Construction Manager that sufficient funds are available and committed for the entire cost of ...
What people are saying - Write a review
We haven't found any reviews in the usual places.
Contents
Construction Industry and Practice | 3 |
Development and Organization of Projects | 14 |
Applications and Requirements for Management | 41 |
Copyright | |
31 other sections not shown
Other editions - View all
Common terms and phrases
activities actual additional Agreement alternative amount applicable approach Architect associated award basic become budget building changes chapter claims companies compared completion concept concrete contract Contract Documents contractor cost delays detail determine developed direct Documents drawings effect employees engineering equipment estimate evaluation example factors field Figure final finish firms impact important increase individual industry involved labor limited major materials methods negotiated normally operations organization overall owner parties payment percent performance period phase planning practices prepared problems procedures procurement productivity professional construction manager progress proposed quantities rates reasonable representative responsibility result risk safety savings schedule scope selection shown shows similar Special specifications standard structure Subcontractor summary Trade union unit utilized