Professional Construction ManagementThe subjects covered in this book include those normally studied in an introductory overview course on construction management, and there is enough depth and added material to serve as the basis for a more advanced course, focusing on organizational and contractual approaches to project management, and the related planning and control systems. This new edition strengthens its coverage of the business aspects of the industry, with a section devoted solely to the business methods in professional construction management. The text's practical in-depth approach to the major engineering and management techniques appeals to both students and practitioners alike. |
From inside the book
Results 1-3 of 96
Page 140
Some of these items include the following : An estimate of total man - hours of field effort required Estimated quantities for major items An estimate of reasonable unit costs for various components of the work Information for ...
Some of these items include the following : An estimate of total man - hours of field effort required Estimated quantities for major items An estimate of reasonable unit costs for various components of the work Information for ...
Page 211
It is helpful to complete the fair - cost estimate well before receiving bids or before performance of the changed work . For an example of the fair - cost estimates for the Mountaintown Warehouse Project , refer back to Appendix A. The ...
It is helpful to complete the fair - cost estimate well before receiving bids or before performance of the changed work . For an example of the fair - cost estimates for the Mountaintown Warehouse Project , refer back to Appendix A. The ...
Page 215
On negotiated projects featuring a guaranteed maximum price , the definitive estimate can generally be prepared at about the same time as on a negotiated cost- plus - a - fixed - fee project . Because one entity is performing both ...
On negotiated projects featuring a guaranteed maximum price , the definitive estimate can generally be prepared at about the same time as on a negotiated cost- plus - a - fixed - fee project . Because one entity is performing both ...
What people are saying - Write a review
We haven't found any reviews in the usual places.
Contents
Construction Industry and Practice | 3 |
Development and Organization of Projects | 14 |
Applications and Requirements for Management | 41 |
Copyright | |
31 other sections not shown
Other editions - View all
Common terms and phrases
activities actual additional Agreement alternative amount applicable approach Architect associated award basic become budget building changes chapter claims companies compared completion concept concrete contract Contract Documents contractor cost delays detail determine developed direct Documents drawings effect employees engineering equipment estimate evaluation example factors field Figure final finish firms impact important increase individual industry involved labor limited major materials methods negotiated normally operations organization overall owner parties payment percent performance period phase planning practices prepared problems procedures procurement productivity professional construction manager progress proposed quantities rates reasonable representative responsibility result risk safety savings schedule scope selection shown shows similar Special specifications standard structure Subcontractor summary Trade union unit utilized