Professional Construction ManagementThe subjects covered in this book include those normally studied in an introductory overview course on construction management, and there is enough depth and added material to serve as the basis for a more advanced course, focusing on organizational and contractual approaches to project management, and the related planning and control systems. This new edition strengthens its coverage of the business aspects of the industry, with a section devoted solely to the business methods in professional construction management. The text's practical in-depth approach to the major engineering and management techniques appeals to both students and practitioners alike. |
From inside the book
Results 1-3 of 88
Page 156
This figure is then compared to the bid price adjusted for change orders to determine anticipated profit and loss in a manner illustrated by Figure 8-2 . SCHEDULE AND PROGRESS CONTROLS BY CONCRETE CONTRACTOR The concrete contractor ...
This figure is then compared to the bid price adjusted for change orders to determine anticipated profit and loss in a manner illustrated by Figure 8-2 . SCHEDULE AND PROGRESS CONTROLS BY CONCRETE CONTRACTOR The concrete contractor ...
Page 261
Progress ( percent completed ) 100 % Projected progress Current lead in progress Actual progress FIGURE 12-7 Planning and reporting progress . Current Planned progress time lead Planned completion date Projected completion date Time ...
Progress ( percent completed ) 100 % Projected progress Current lead in progress Actual progress FIGURE 12-7 Planning and reporting progress . Current Planned progress time lead Planned completion date Projected completion date Time ...
Page 272
B 3 C 4 FIGURE 12-17 Beginning of arrow network . Referring to the Followers column in Table 12-1 , activity A is followed by D and E. Activity A , in turn , is the sole predecessor of D and E. Similarly , F follows C , and C is the ...
B 3 C 4 FIGURE 12-17 Beginning of arrow network . Referring to the Followers column in Table 12-1 , activity A is followed by D and E. Activity A , in turn , is the sole predecessor of D and E. Similarly , F follows C , and C is the ...
What people are saying - Write a review
We haven't found any reviews in the usual places.
Contents
Construction Industry and Practice | 3 |
Development and Organization of Projects | 14 |
Applications and Requirements for Management | 41 |
Copyright | |
31 other sections not shown
Other editions - View all
Common terms and phrases
activities actual additional Agreement alternative amount applicable approach Architect associated award basic become budget building changes chapter claims companies compared completion concept concrete contract Contract Documents contractor cost delays detail determine developed direct Documents drawings effect employees engineering equipment estimate evaluation example factors field Figure final finish firms impact important increase individual industry involved labor limited major materials methods negotiated normally operations organization overall owner parties payment percent performance period phase planning practices prepared problems procedures procurement productivity professional construction manager progress proposed quantities rates reasonable representative responsibility result risk safety savings schedule scope selection shown shows similar Special specifications standard structure Subcontractor summary Trade union unit utilized