Professional Construction Management |
From inside the book
Results 1-3 of 79
Page 135
A simplified CPM precedence diagram giving the construction schedule for the example project is shown in Appendix A. Figure 8-8 shows a bar - chart schedule , fully consistent with the CPM , upon which superimposed S curves show ...
A simplified CPM precedence diagram giving the construction schedule for the example project is shown in Appendix A. Figure 8-8 shows a bar - chart schedule , fully consistent with the CPM , upon which superimposed S curves show ...
Page 199
However , to illustrate briefly the money side for overtime and shift differentials , the alternatives are shown on Figure 11-6 . Curve A shows the average hourly wages for working 8 hours straight time at $ 10 per hour .
However , to illustrate briefly the money side for overtime and shift differentials , the alternatives are shown on Figure 11-6 . Curve A shows the average hourly wages for working 8 hours straight time at $ 10 per hour .
Page 229
Essentially , what it shows is a section of the system intended to go " on - line " as a unit , at the same date , for revenue service . The section may consist of several stations and connecting sections of grade , subway , or aerial ...
Essentially , what it shows is a section of the system intended to go " on - line " as a unit , at the same date , for revenue service . The section may consist of several stations and connecting sections of grade , subway , or aerial ...
What people are saying - Write a review
We haven't found any reviews in the usual places.
Contents
The Nature of the Construction Industry | 6 |
What Is Professional Construction Management? | 13 |
MANAGEMENT IN PRACTICE | 15 |
Copyright | |
21 other sections not shown
Other editions - View all
Common terms and phrases
acceptance activities actual additional Agreement alternative amount applicable approach approval Architect award basic bidders budget building changes Chapter chart compared completion concepts concrete considerations contract contractor cost detailed determine developed direct documents drawings economic effect engineering equipment estimate evaluation example facilities factors field Figure finish firms important individual industry inspection involved knowledge labor major materials methods needed negotiated objectives obtain operations organization overall owner packages payment percent performance period phase planning plant practices preliminary prepared problems procedures procurement productivity professional construction manager progress proposed quantities reasonable reports responsibilities safety savings schedule scope selection separate shows Special specifications standard Structural subcontractors testing tion Trade traditional unassigned unit utilities value engineering warehouse