Professional Construction Management |
From inside the book
Results 1-3 of 90
Page 84
The preliminary estimate is also necessary for preparing a realistic overall project schedule that forecasts occupancy dates and specifies completion schedules for individual construction contracts . The preliminary estimate forms the ...
The preliminary estimate is also necessary for preparing a realistic overall project schedule that forecasts occupancy dates and specifies completion schedules for individual construction contracts . The preliminary estimate forms the ...
Page 85
time is planned from the beginning , schedules can be more easily met , and more competitive bids will normally be ... a reasonable period for evaluation and award of each bid package should therefore be included in the schedule .
time is planned from the beginning , schedules can be more easily met , and more competitive bids will normally be ... a reasonable period for evaluation and award of each bid package should therefore be included in the schedule .
Page 135
SCHEDULE AND PROGRESS CONTROLS Control schedules are developed and refined through preparation and revision of the overall plan . As project construction proceeds , it is evident that actual accomplishments must be compared with the ...
SCHEDULE AND PROGRESS CONTROLS Control schedules are developed and refined through preparation and revision of the overall plan . As project construction proceeds , it is evident that actual accomplishments must be compared with the ...
What people are saying - Write a review
We haven't found any reviews in the usual places.
Contents
The Nature of the Construction Industry | 6 |
What Is Professional Construction Management? | 13 |
MANAGEMENT IN PRACTICE | 15 |
Copyright | |
21 other sections not shown
Other editions - View all
Common terms and phrases
acceptance activities actual additional Agreement alternative amount applicable approach approval Architect award basic bidders budget building changes Chapter chart compared completion concepts concrete considerations contract contractor cost detailed determine developed direct documents drawings economic effect engineering equipment estimate evaluation example facilities factors field Figure finish firms important individual industry inspection involved knowledge labor major materials methods needed negotiated objectives obtain operations organization overall owner packages payment percent performance period phase planning plant practices preliminary prepared problems procedures procurement productivity professional construction manager progress proposed quantities reasonable reports responsibilities safety savings schedule scope selection separate shows Special specifications standard Structural subcontractors testing tion Trade traditional unassigned unit utilities value engineering warehouse