Professional Construction Management |
From inside the book
Results 1-3 of 30
Page 169
CODE D SF CFF.0310 CONCRETE FORMWORK FOR FOUNDATION EST START : 06/02/75 DURATION : ACT START : 06/02/75 COSTS : EST FINISH : 07/18/75 QUANTITIES : ACT FINISH : UNIT COSTS : 34 $ 24900 15860 $ 1.57 29 $ 23800 13600 $ 1.75 9 $ 7450 4150 ...
CODE D SF CFF.0310 CONCRETE FORMWORK FOR FOUNDATION EST START : 06/02/75 DURATION : ACT START : 06/02/75 COSTS : EST FINISH : 07/18/75 QUANTITIES : ACT FINISH : UNIT COSTS : 34 $ 24900 15860 $ 1.57 29 $ 23800 13600 $ 1.75 9 $ 7450 4150 ...
Page 174
He must assess quantities not only of the contract materials reflected in the drawings , but also of the temporary materials , such as formwork for concrete and temporary plant . The latter estimates , in turn , require that the ...
He must assess quantities not only of the contract materials reflected in the drawings , but also of the temporary materials , such as formwork for concrete and temporary plant . The latter estimates , in turn , require that the ...
Page 174
He must assess quantities not only of the contract materials reflected in the drawings , but also of the temporary materials , such as formwork for concrete and temporary plant . The latter estimates , in turn , require that the ...
He must assess quantities not only of the contract materials reflected in the drawings , but also of the temporary materials , such as formwork for concrete and temporary plant . The latter estimates , in turn , require that the ...
What people are saying - Write a review
We haven't found any reviews in the usual places.
Contents
The Nature of the Construction Industry | 6 |
What Is Professional Construction Management? | 13 |
MANAGEMENT IN PRACTICE | 15 |
Copyright | |
21 other sections not shown
Other editions - View all
Common terms and phrases
acceptance activities actual additional Agreement alternative amount applicable approach approval Architect award basic bidders budget building changes Chapter chart compared completion concepts concrete considerations contract contractor cost detailed determine developed direct documents drawings economic effect engineering equipment estimate evaluation example facilities factors field Figure finish firms important individual industry inspection involved knowledge labor major materials methods needed negotiated objectives obtain operations organization overall owner packages payment percent performance period phase planning plant practices preliminary prepared problems procedures procurement productivity professional construction manager progress proposed quantities reasonable reports responsibilities safety savings schedule scope selection separate shows Special specifications standard Structural subcontractors testing tion Trade traditional unassigned unit utilities value engineering warehouse