Professional Construction Management |
From inside the book
Results 1-3 of 88
Page 167
Selectivity and subreporting are important here . Since time is among their scarcest resources , construction managers and supervisors simply cannot afford to wade through piles of extraneous data to obtain the information they need .
Selectivity and subreporting are important here . Since time is among their scarcest resources , construction managers and supervisors simply cannot afford to wade through piles of extraneous data to obtain the information they need .
Page 264
Another important concept was implied in the discussion of learning curves in Chapter 10 , and was amplified in Chapter 11. Estimates necessarily must be based on averages . However , if one controls only against averages , one might ...
Another important concept was implied in the discussion of learning curves in Chapter 10 , and was amplified in Chapter 11. Estimates necessarily must be based on averages . However , if one controls only against averages , one might ...
Page 308
An important feature of value engineering is life - cycle costing ; this allows for the effect of future operational , overhead , carrying , and maintenance costs as well as initial capital or construction costs .
An important feature of value engineering is life - cycle costing ; this allows for the effect of future operational , overhead , carrying , and maintenance costs as well as initial capital or construction costs .
What people are saying - Write a review
We haven't found any reviews in the usual places.
Contents
The Nature of the Construction Industry | 6 |
What Is Professional Construction Management? | 13 |
MANAGEMENT IN PRACTICE | 15 |
Copyright | |
21 other sections not shown
Other editions - View all
Common terms and phrases
acceptance activities actual additional Agreement alternative amount applicable approach approval Architect award basic bidders budget building changes Chapter chart compared completion concepts concrete considerations contract contractor cost detailed determine developed direct documents drawings economic effect engineering equipment estimate evaluation example facilities factors field Figure finish firms important individual industry inspection involved knowledge labor major materials methods needed negotiated objectives obtain operations organization overall owner packages payment percent performance period phase planning plant practices preliminary prepared problems procedures procurement productivity professional construction manager progress proposed quantities reasonable reports responsibilities safety savings schedule scope selection separate shows Special specifications standard Structural subcontractors testing tion Trade traditional unassigned unit utilities value engineering warehouse