Professional Construction Management |
From inside the book
Results 1-3 of 89
Page 176
Most of the existing conceptual and preliminary estimating methods fall into one or more of the following categories : 1 Time - referenced cost indices 2 Cost - capacity factors 3 Component ratios 4 Parameter costs They are listed ...
Most of the existing conceptual and preliminary estimating methods fall into one or more of the following categories : 1 Time - referenced cost indices 2 Cost - capacity factors 3 Component ratios 4 Parameter costs They are listed ...
Page 213
Techniques examined for conceptual and preliminary estimates were ( 1 ) cost indices , ( 2 ) cost - capacity factors ... Cost indices mainly reflect time - dependent changes in costs resulting from inflation , changes in technology ...
Techniques examined for conceptual and preliminary estimates were ( 1 ) cost indices , ( 2 ) cost - capacity factors ... Cost indices mainly reflect time - dependent changes in costs resulting from inflation , changes in technology ...
Page 447
Cost codes : bulk materials codes , 258,259 clearing account , 258,259 concepts and principles , 249–262 direct costs , 256-257 distribution code , 255 holding account , 258,259 indirect costs , 256-257 prime account , 255-256 project ...
Cost codes : bulk materials codes , 258,259 clearing account , 258,259 concepts and principles , 249–262 direct costs , 256-257 distribution code , 255 holding account , 258,259 indirect costs , 256-257 prime account , 255-256 project ...
What people are saying - Write a review
We haven't found any reviews in the usual places.
Contents
The Nature of the Construction Industry | 6 |
What Is Professional Construction Management? | 13 |
MANAGEMENT IN PRACTICE | 15 |
Copyright | |
21 other sections not shown
Other editions - View all
Common terms and phrases
acceptance activities actual additional Agreement alternative amount applicable approach approval Architect award basic bidders budget building changes Chapter chart compared completion concepts concrete considerations contract contractor cost detailed determine developed direct documents drawings economic effect engineering equipment estimate evaluation example facilities factors field Figure finish firms important individual industry inspection involved knowledge labor major materials methods needed negotiated objectives obtain operations organization overall owner packages payment percent performance period phase planning plant practices preliminary prepared problems procedures procurement productivity professional construction manager progress proposed quantities reasonable reports responsibilities safety savings schedule scope selection separate shows Special specifications standard Structural subcontractors testing tion Trade traditional unassigned unit utilities value engineering warehouse