Professional Construction Management |
From inside the book
Results 1-3 of 44
Page 47
... and procurement schedule showing actual progress compared with that scheduled CPM summary schedule showing actual contract progress compared with scheduled progress for each contract Cost report comparing forecast - at - completion ...
... and procurement schedule showing actual progress compared with that scheduled CPM summary schedule showing actual contract progress compared with scheduled progress for each contract Cost report comparing forecast - at - completion ...
Page 135
As project construction proceeds , it is evident that actual accomplishments must be compared with the overall plan if effective control is to be achieved . Many items discussed in cost control are equally applicable to progress control ...
As project construction proceeds , it is evident that actual accomplishments must be compared with the overall plan if effective control is to be achieved . Many items discussed in cost control are equally applicable to progress control ...
Page 206
When a truly integrated management control system is utilized , actual man - hours can be compared to estimated man - hours , and actual productivity for components and for the entire project can be easily measured .
When a truly integrated management control system is utilized , actual man - hours can be compared to estimated man - hours , and actual productivity for components and for the entire project can be easily measured .
What people are saying - Write a review
We haven't found any reviews in the usual places.
Contents
The Nature of the Construction Industry | 6 |
What Is Professional Construction Management? | 13 |
MANAGEMENT IN PRACTICE | 15 |
Copyright | |
21 other sections not shown
Other editions - View all
Common terms and phrases
acceptance activities actual additional Agreement alternative amount applicable approach approval Architect award basic bidders budget building changes Chapter chart compared completion concepts concrete considerations contract contractor cost detailed determine developed direct documents drawings economic effect engineering equipment estimate evaluation example facilities factors field Figure finish firms important individual industry inspection involved knowledge labor major materials methods needed negotiated objectives obtain operations organization overall owner packages payment percent performance period phase planning plant practices preliminary prepared problems procedures procurement productivity professional construction manager progress proposed quantities reasonable reports responsibilities safety savings schedule scope selection separate shows Special specifications standard Structural subcontractors testing tion Trade traditional unassigned unit utilities value engineering warehouse